High risk
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2022 per the RERA filing.
Satellite view of this address

Where it is · 546, Wadhe

Promoter

Builder profile

Builder
Shirke Constructions Pvt. Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52700013367
Status
New
Stage
Certificate Signed
Possession
September 2022
Construction
0% complete
Units sold
0 of 0