Under construction

SAI SADAN

MahaRERA P52800077065Caution

by ADITH BUILDERS AND DEVELOPERS

29/1B, 29/1A1A/4, CAMP DAPOLI, CS NO.2296,2297,2298, CAMP DAPOLI, 415712

Official record
May 2028
Possession
37.1%
Built
0
Complaints
42
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Jan 2026, now proposed May 2028 per the RERA filing.
Satellite view of this address

Where it is · 29/1B, 29/1A1A/4, CAMP DAPOLI, CS NO.2296,2297,2298, CAMP DAPOLI

Promoter

Builder profile

Builder
ADITH BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52800077065
Status
New
Stage
Certificate Signed
Possession
May 2028originally January 2026
Construction
37.1% complete
Units sold
8 of 42

Similar projects in CAMP DAPOLI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how CAMP DAPOLI compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.