Under construction

Samarth Orchid

MahaRERA P52800025686High risk

by Shree Samarthkrupa Builders & Developers

Survey No. 29A1A11A1E1C, 291A1A1A1A23 and 291A1A2, and CTS No 2310 to 2313, Dapoli Camp, 415712

Official record
Dec 2026
Possession
82.3%
Built
0
Complaints
75
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Area guide

What it's like to buy in Dapoli Camp

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Shree Samarthkrupa Builders & Developers

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Ravindra Mahadeo Patil

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52800025686
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2025
Construction
82.3% complete
Units sold
46 of 75

Similar projects in Dapoli Camp

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Dapoli Camp compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.