SAMARTH RECEDENCY
MahaRERA P52700016134High risk
by URMODI BUILDER & DEVELOPERS
34/1/2, Jakatwadi, 415002
Post your property hereOwn or renting out a unit in SAMARTH RECEDENCY? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Jakatwadi come to you.
Aug 2025
Possession
88.2%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Sept 2022, now proposed Aug 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Aug 2025) has passed with construction at 88.2%.
Satellite view of this address
Where it is · 34/1/2, Jakatwadi
Promoter
Builder profile
URMODI BUILDER & DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52700016134
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2025originally September 2022
- Construction
- 88.2% complete
- Units sold
- 0 of 0
Similar projects in Jakatwadi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
RAJLAXMI HEIGHTS
Jakatwadi100% builtPoss. July 2023
Shourya Heights
Jakatwadi81.8% builtPoss. January 2024
Keep exploring
Where this project sits, who built it, and how Jakatwadi compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.