Under construction
SANSKRUTI PARK
MahaRERA P52900001092High risk
Survey No 253/18/9, 253/18/10, 253/18/11, Malwan (M Cl), 416606
Post your property hereOwn or renting out a unit in SANSKRUTI PARK? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Malwan (M Cl) come to you.
Dec 2021
Possession
62.7%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 62.7%.
Satellite view of this address
Where it is · Survey No 253/18/9, 253/18/10, 253/18/11, Malwan (M Cl)
Promoter
Builder profile
SANSKRUTI INFRASTRUCTURE
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52900001092
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally December 2019
- Construction
- 62.7% complete
- Units sold
- 0 of 0
Similar projects in Malwan (M Cl)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Coral Residency B
Malwan (M Cl)90.9% builtPoss. October 2019
SAMARTH ANGAN
Malwan (M Cl)90.9% builtPoss. June 2019
PRIDE SQUARE
Malwan (M Cl)89.1% builtPoss. June 2018
PRIDE SIGNATURE
Malwan (M Cl)78.4% builtPoss. December 2022
Shree Samarth Residency
Malwan (M Cl)51.4% builtPoss. October 20201 complaint
RUTURAJ EMPIRE
Malwan (M Cl)18.2% builtPoss. November 2020
Keep exploring
Where this project sits, who built it, and how Malwan (M Cl) compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.