Under construction
SARASWATI PLAZA
MahaRERA P52800011053High risk
CTS 6021 AND SNO54-4, Chiplun (M Cl), 415605
Post your property hereOwn or renting out a unit in SARASWATI PLAZA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Chiplun (M Cl) come to you.
Jan 2021
Possession
27.3%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jan 2021) has passed with construction at 27.3%.
Satellite view of this address
Where it is · CTS 6021 AND SNO54-4, Chiplun (M Cl)
Promoter
Builder profile
DILIP PYARELAL JAIN
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52800011053
- Status
- New
- Stage
- Certificate Signed
- Possession
- January 2021
- Construction
- 27.3% complete
- Units sold
- 0 of 0
Similar projects in Chiplun (M Cl)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
CAPITAL HEIGHTS
Chiplun (M Cl)100% builtPoss. December 2023
Ramkrishna Plaza - C Building
Chiplun (M Cl)90.9% builtPoss. December 2021
PRITIVARDHAN PLAZA
Chiplun (M Cl)90.9% builtPoss. January 2021
VIRALI APARTMENT
Chiplun (M Cl)90.9% builtPoss. December 2019
PATEL TRADE CENTER
Chiplun (M Cl)90.9% builtPoss. December 2023
Orchid
Chiplun (M Cl)89.5% builtPoss. December 2017
Desai Enclave
Chiplun (M Cl)89.1% builtPoss. April 2018
KADAMBARI
Chiplun (M Cl)88.6% builtPoss. December 2028
Keep exploring
Where this project sits, who built it, and how Chiplun (M Cl) compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.