Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 25.6%.
Satellite view of this address

Where it is · 1+2 S No 509-3, EKNATH NAGAR

Area guide

What it's like to buy in EKNATH NAGAR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SARASWATI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52200053013
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
25.6% complete
Units sold
28 of 53

Similar projects in EKNATH NAGAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how EKNATH NAGAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.