High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2023, now proposed Sept 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 0%.

Promoter

Builder profile

Builder
Vijaysinha Krishnarao Parbat

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53100019708
Status
New
Stage
Certificate Signed
Possession
September 2024originally March 2023
Construction
0% complete
Units sold
0 of 0