Under construction
Shamji Ladha
MahaRERA P51900018276High risk
283/10, Mumbai City, 400019
Post your property hereOwn or renting out a unit in Shamji Ladha? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Mumbai City come to you.
Aug 2023
Possession
81.1%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Aug 2023) has passed with construction at 81.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2023 per the RERA filing.
Promoter
Builder profile
Endemic Realtors Pvt. Ltd
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51900018276
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2023
- Construction
- 81.1% complete
- Units sold
- 0 of 0
Similar projects in Mumbai City
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
BKC EDGE
Mumbai CityPoss. April 20303 complaints
Q GARDENS REALTY
Mumbai CityPoss. July 2019
1515 Moneco
Mumbai CityPoss. September 20261 complaint
Salsette27 Centre
Mumbai CityPoss. July 2028
Lodha Promina
Mumbai CityPoss. October 2032
Dhuleva Business Bay
Mumbai CityPoss. April 2031
ARIA SKYGARDENS
Mumbai CityPoss. September 2030
Sanghvi Parsssva Elysium
Mumbai CityPoss. April 2030
Keep exploring
Where this project sits, who built it, and how Mumbai City compares.
In Mumbai City
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.