Under construction
SHIV OM PLAZA
MahaRERA P52800001921High risk
S NO 103A H NO 2/82 H NO 2/83, Khedshi, 415639
Post your property hereOwn or renting out a unit in SHIV OM PLAZA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Khedshi come to you.
Jul 2019
Possession
44.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jul 2019) has passed with construction at 44.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2019 per the RERA filing.
Satellite view of this address
Where it is · S NO 103A H NO 2/82 H NO 2/83, Khedshi
Promoter
Builder profile
SHIVSHAKTI ENTERPRISES
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52800001921
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- July 2019
- Construction
- 44.5% complete
- Units sold
- 0 of 0
Similar projects in Khedshi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Pushpendra City- Mahalakshmi Presidency
Khedshi90.9% builtPoss. June 2022
Pushpendra City- Mahalakshmi Enclave
Khedshi90.9% builtPoss. June 2022
Swarupa Residency
Khedshi90.9% builtPoss. November 2018
SUMUKHAY RESIDENCY
Khedshi90.9% builtPoss. December 2024
Navkar Mahalaxmi Enclave
Khedshi84.5% builtPoss. December 2018
Pushpendra City - Sector 10
Khedshi83.6% builtPoss. June 2028
ANANYA
Khedshi81.8% builtPoss. August 2024
SADGURU ASHISH
Khedshi63.6% builtPoss. March 2025
Keep exploring
Where this project sits, who built it, and how Khedshi compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.