SHIVAJI SANKUL 5
S. NO. 24/2, 24/1 B, 24/1 C, 24/1 D, PLOT NO. 15 A, 7, 5 PART, 6 PART, AMRAVATI, 444607
- Possession delayed ~5 yrs. Originally promised Sept 2024, now proposed Nov 2029 per the RERA filing.
Where it is · S. NO. 24/2, 24/1 B, 24/1 C, 24/1 D, PLOT NO. 15 A, 7, 5 PART, 6 PART, AMRAVATI
Area guide
What it's like to buy in AMRAVATI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P50300010727
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2029originally September 2024
- Construction
- 27% complete
- Units sold
- 0 of 0
Similar projects in AMRAVATI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how AMRAVATI compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.