Dec 2019
Possession
67.3%
Built
3
Complaints
0
Units
High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 67.3%.
Satellite view of this address

Where it is · S.NO165A117A2121,165A117A2122. CTS NO 68, Chiplun (M Cl)

Area guide

What it's like to buy in Chiplun (M Cl)

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
DEEPAK PANDURANG BHALEKAR

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52800013453
Status
Ongoing
Stage
Certificate Signed
Possession
December 2019
Construction
67.3% complete
Units sold
0 of 0

Similar projects in Chiplun (M Cl)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Chiplun (M Cl) compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.