- Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 58.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.
Where it is · survey no 100 hiss no 1, CHIPLUN
Area guide
What it's like to buy in CHIPLUN
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P52800021445
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2025
- Construction
- 58.5% complete
- Units sold
- 23 of 48
Similar projects in CHIPLUN
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how CHIPLUN compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.