Under construction

SHREE COMPLEX

MahaRERA P52800047959Caution

by Yogesh Shashikant Kudalkar

Survey No. 282/A1/1A1A1A1/64B, 282/A1/1A1A1A1/63/1, 194/A1A1A1A1A1/3B, 194/A1A1A1A1A1/3A, CTS NO. 2731, 2732, 2733, 2734, Mauje Khed, 415709

Official record
Apr 2027
Possession
90.6%
Built
0
Complaints
60
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Oct 2025, now proposed Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · Survey No. 282/A1/1A1A1A1/64B, 282/A1/1A1A1A1/63/1, 194/A1A1A1A1A1/3B, 194/A1A1A1A1A1/3A, CTS NO. 2731, 2732, 2733, 2734, Mauje Khed

Promoter

Builder profile

Builder
Yogesh Shashikant Kudalkar

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Shrish S Ghorpade

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52800047959
Status
New
Stage
Certificate Signed
Possession
April 2027originally October 2025
Construction
90.6% complete
Units sold
12 of 60

Keep exploring

Where this project sits, who built it, and how Mauje Khed compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.