High risk
  • Possession date passed. The proposed possession date (Sept 2018) has passed with construction at 74.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2018 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO 127,, Sawantwadi (M Cl)

Promoter

Builder profile

Builder
ARCHANA SANDEEP GHARE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52900014070
Status
Ongoing
Stage
Certificate Signed
Possession
September 2018
Construction
74.5% complete
Units sold
0 of 0

Similar projects in Sawantwadi (M Cl)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Sawantwadi (M Cl) compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.