Under construction
Shree Laxmi Complex
MahaRERA P52700022132High risk
CTS No 10, Satara, 415002
Post your property hereOwn or renting out a unit in Shree Laxmi Complex? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Satara come to you.
Oct 2025
Possession
39.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Oct 2025) has passed with construction at 39.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2025 per the RERA filing.
Promoter
Builder profile
NANDKUMAR VINAYAK PHADKE
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52700022132
- Status
- New
- Stage
- Certificate Signed
- Possession
- October 2025
- Construction
- 39.5% complete
- Units sold
- 0 of 0
Similar projects in Satara
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Aishwarya Nagari
SataraPoss. April 2019
Aishwarya Empire
SataraPoss. September 2024
Sukhodayam Villas
SataraPoss. April 2028
Parijat Skyline
SataraPoss. August 2028
Vasundhara
SataraPoss. April 2029
Kirtiban
SataraPoss. December 2030
Rugved
SataraPoss. April 2030
Shree Gulab Pushp
Satara100% builtPoss. December 2022
Keep exploring
Where this project sits, who built it, and how Satara compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.