Under construction

Shree Om Co-Op. Housing Society Ltd

MahaRERA P51900024467High risk

by KING DEVELOPERS

316,316/1-6, Goregaon East, 400063

Official record
Dec 2023
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Promoter

Builder profile

Builder
KING DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51900024467
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
0% complete
Units sold
0 of 0

Similar projects in Goregaon East

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Goregaon East compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.