High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • Possession delayed ~7 yrs. Originally promised Dec 2019, now proposed Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · 1-115, 115, Ward E

Promoter

Builder profile

Builder
SHREEPATI BUILD INFRA INVESTMENT LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51900000623
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally December 2019
Construction
80.2% complete
Units sold
0 of 0

Similar projects in Ward E

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ward E compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.