High risk
  • Possession date passed. The proposed possession date (Jul 2019) has passed with construction at 94.5%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jul 2019 per the RERA filing.
Satellite view of this address

Where it is · SECTOR NO 138P, Pisadevi

Promoter

Builder profile

Builder
SHRI JAIDATT BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51500004078
Status
Ongoing
Stage
Certificate Signed
Possession
July 2019
Construction
94.5% complete
Units sold
0 of 0

Similar projects in Pisadevi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pisadevi compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.