Under construction
SHRI MARYAMBI VANSH PARK
MahaRERA P52800013301High risk
26/A/1/4, Shringartali, 415724
Post your property hereOwn or renting out a unit in SHRI MARYAMBI VANSH PARK? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Shringartali come to you.
Jun 2023
Possession
35.5%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Jun 2023 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 35.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.
Satellite view of this address
Where it is · 26/A/1/4, Shringartali
Promoter
Builder profile
NARENDRA NAMDEO DHADVE
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52800013301
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2023originally December 2019
- Construction
- 35.5% complete
- Units sold
- 0 of 0
Similar projects in Shringartali
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
GOLDEN HEIGHTS
ShringartaliPoss. December 2029
GARGI APARTMENT
Shringartali90.9% builtPoss. December 2022
Star City
Shringartali51.8% builtPoss. June 2019
VITHOBA RESIDENCY
Shringartali50.5% builtPoss. December 2027
BUTLER COMPLEX
Shringartali40% builtPoss. December 2026
INDRADITYA
Shringartali9.1% builtPoss. December 2028
BAMNE TOWER
Shringartali0% builtPoss. December 2028
Keep exploring
Where this project sits, who built it, and how Shringartali compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.