High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 179/B-12 AND 179/A-23, NEAR KANKAVLI RAILWAY STATION

Promoter

Builder profile

Builder
KISHOR SHAHU PANGAM

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52900033456
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
27.3% complete
Units sold
0 of 0