SHRI SIDHESHWAR COMPLEX
SURVYE NO 104 HISSA NO 39 B 39C 21 38 21A 38 21 C, Kolgaon, 416510
- Possession delayed ~8 yrs. Originally promised Oct 2018, now proposed Nov 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.
Where it is · SURVYE NO 104 HISSA NO 39 B 39C 21 38 21A 38 21 C, Kolgaon
Area guide
What it's like to buy in Kolgaon
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52900012882
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- November 2026originally October 2018
- Construction
- 55.5% complete
- Units sold
- 0 of 0
Similar projects in Kolgaon
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kolgaon compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.