Under construction

SHRI SIDHESHWAR COMPLEX

MahaRERA P52900012882High risk

by RADHEY ENTERPRISES

SURVYE NO 104 HISSA NO 39 B 39C 21 38 21A 38 21 C, Kolgaon, 416510

Official record
Nov 2026
Possession
55.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Oct 2018, now proposed Nov 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.
Satellite view of this address

Where it is · SURVYE NO 104 HISSA NO 39 B 39C 21 38 21A 38 21 C, Kolgaon

Promoter

Builder profile

Builder
RADHEY ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52900012882
Status
Ongoing
Stage
Certificate Signed
Possession
November 2026originally October 2018
Construction
55.5% complete
Units sold
0 of 0

Similar projects in Kolgaon

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kolgaon compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.