High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Possession date passed. The proposed possession date (Aug 2022) has passed with construction at 81.8%.
Satellite view of this address

Where it is · 13192 6 7 1, BAPAT MALA

Promoter

Builder profile

Builder
SHRI SIDDHAKALA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53100015441
Status
New
Stage
Certificate Signed
Possession
August 2022
Construction
81.8% complete
Units sold
0 of 0

Similar projects in BAPAT MALA

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how BAPAT MALA compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.