SHWESH CHAMPARAN
by SHWESH DEVELOPERS PRIVATE LIMITED
712B/10, MATUNGA EAST, 400019
- Possession delayed ~1 yr. Originally promised Dec 2024, now proposed Mar 2026 per the RERA filing.
- Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 47.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2026 per the RERA filing.
Where it is · 712B/10, MATUNGA EAST
Area guide
What it's like to buy in MATUNGA EAST
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Old central Bombay — colleges, gardens and society redevelopment.
- Growth drivers:
- Central location, rail junctions, redevelopment of 60s societies.
- Who buys here:
- Central-line families and South Indian community roots.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51900033818
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2026originally December 2024
- Construction
- 47.1% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how MATUNGA EAST compares.
In MATUNGA EAST
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.