Under construction

Siddha Sky Phase 4

MahaRERA P51900021031High risk

by Sejal Shakti Realtors LLP

6 pt, 16 pt to 21 pt of salt pan division and 12 pt of sion division, Mumbai City, 400037

Official record
Dec 2030
Possession
3.6%
Built
2
Complaints
365
Units
High risk
  • Possession delayed ~4 yrs. Originally promised May 2027, now proposed Dec 2030 per the RERA filing.

Area guide

What it's like to buy in Mumbai City

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Sejal Shakti Realtors LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51900021031
Status
New
Stage
Certificate Signed
Possession
December 2030originally May 2027
Construction
3.6% complete
Units sold
45 of 365

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mumbai City compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.