High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2017, now proposed Jun 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 90.9%.
Satellite view of this address

Where it is · Part Gut No 14, Fattepur

Promoter

Builder profile

Builder
ASCENTVENTURES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51500005615
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023originally December 2017
Construction
90.9% complete
Units sold
0 of 0