Jun 2018
Possession
61.4%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 61.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2018 per the RERA filing.
Satellite view of this address
Where it is · 42/1 JEWAD BADNERA PLOT NO 10A 10B 11A, Amravati (M Corp.)
Promoter
Builder profile
NARENDRA PRATAPRAI KINGRANI
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P50300010367
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2018
- Construction
- 61.4% complete
- Units sold
- 0 of 0
Similar projects in Amravati (M Corp.)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
UDAY NAGAR LAYOUT A
Amravati (M Corp.)Poss. October 2019
UDAY NAGAR LAYOUT D
Amravati (M Corp.)Poss. October 2019
UDAY PARK - LAYOUT C
Amravati (M Corp.)Poss. October 2019
UDAY NAGAR -LAYOUT B
Amravati (M Corp.)Poss. October 2019
GOVINDA CITY - 1
Amravati (M Corp.)Poss. March 2019
SHIVANAND HEIGHTS
Amravati (M Corp.)100% builtPoss. February 2023
RASHI TRINITY
Amravati (M Corp.)100% builtPoss. May 2018
Shri Radha Krishna Residency
Amravati (M Corp.)100% builtPoss. March 2019
Keep exploring
Where this project sits, who built it, and how Amravati (M Corp.) compares.
In Amravati (M Corp.)
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.