Apr 2029
Possession
49.1%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Mar 2026, now proposed Apr 2029 per the RERA filing.
Satellite view of this address
Where it is · 143-1-2-5-2, Godoli (CT)
Promoter
Builder profile
Vedant Infra
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52700004436
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- April 2029originally March 2026
- Construction
- 49.1% complete
- Units sold
- 0 of 0
Similar projects in Godoli (CT)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Ajinkya Pushp
Godoli (CT)100% builtPoss. January 2019
Green city Phase 1
Godoli (CT)71.8% builtPoss. December 2021
SIDDHGANESH RESIDENCY
Godoli (CT)69.1% builtPoss. May 2019
AVADHUT VIHAR B WING
Godoli (CT)56.4% builtPoss. December 2018
Keep exploring
Where this project sits, who built it, and how Godoli (CT) compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 28 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.