High risk
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 28.6%.

Promoter

Builder profile

Builder
Mahesh Chandrabhan Kingrani

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P50300031116
Status
New
Stage
Certificate Signed
Possession
September 2022
Construction
28.6% complete
Units sold
0 of 0

Similar projects in Shankar Nagar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Shankar Nagar compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.