High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~7 yrs. Originally promised Sept 2018, now proposed Sept 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 86.8%.
Satellite view of this address

Where it is · Survey No. 410/1, GAT No. 605/1, Shindewadi

Promoter

Builder profile

Builder
EBPL HOMES LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52700013128
Status
Ongoing
Stage
Certificate Signed
Possession
September 2025originally September 2018
Construction
86.8% complete
Units sold
0 of 0

Similar projects in Shindewadi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Shindewadi compares.

Data sourced from the official MahaRERA portal; complaints last synced 18 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.