All RERA projects
🏗️
Under construction

Tridhaatu Arista - Redevelopment of Shanti Niwas

MahaRERA P51900001764High risk

by Tridhaatu Builders LLP

Plot No 269 CS No 19/10, Matunga, 400019

Official record
Mar 2027
Possession
76.8%
Built
2
Complaints
21
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Satellite view of this address

Where it is · Plot No 269 CS No 19/10, Matunga

Area guide

What it's like to buy in Matunga

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Sion / MatungaUpper-mid

Old central Bombay — colleges, gardens and society redevelopment.

Growth drivers:
Central location, rail junctions, redevelopment of 60s societies.
Who buys here:
Central-line families and South Indian community roots.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Tridhaatu Builders LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51900001764
Status
New
Stage
Certificate Signed
Possession
March 2027originally June 2021
Construction
76.8% complete
Units sold
11 of 21

Similar projects in Matunga

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Matunga compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.