Under construction
Tulip Tower
MahaRERA P50400013538High risk
by V4 Infra
15, 16a /44, Chichala, 442001
Post your property hereOwn or renting out a unit in Tulip Tower? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Chichala come to you.
Feb 2021
Possession
81.8%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~1 yr. Originally promised Aug 2019, now proposed Feb 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Feb 2021) has passed with construction at 81.8%.
Satellite view of this address
Where it is · 15, 16a /44, Chichala
Promoter
Builder profile
V4 Infra
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P50400013538
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- February 2021originally August 2019
- Construction
- 81.8% complete
- Units sold
- 0 of 0
Similar projects in Chichala
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Chichala compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.