High risk
  • Possession delayed ~3 yrs. Originally promised Nov 2024, now proposed Apr 2028 per the RERA filing.
Satellite view of this address

Where it is · 22/1, PLOTNO 11 TO 56 & 85 TO 92, TULSIBAAG

Promoter

Builder profile

Builder
SUSHMA SHAILESH KULKARNI

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52400053613
Status
New
Stage
Certificate Signed
Possession
April 2028originally November 2024
Construction
38.2% complete
Units sold
0 of 0