High risk
  • Possession date passed. The proposed possession date (Jul 2021) has passed with construction at 10%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2021 per the RERA filing.

Area guide

What it's like to buy in ujjwal dham

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
NIWARA GRUHNIRMAN PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52400021225
Status
New
Stage
Certificate Signed
Possession
July 2021
Construction
10% complete
Units sold
0 of 0