ULKA SRUSHTI
PLOT NO. 7/ SURVEY NO. 8, Ahmednagar, 414001
- Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.
Where it is · PLOT NO. 7/ SURVEY NO. 8, Ahmednagar
Area guide
What it's like to buy in Ahmednagar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52200031535
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2025
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Ahmednagar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Ahmednagar compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.