High risk
  • Possession date passed. The proposed possession date (Oct 2021) has passed with construction at 43.2%.

Promoter

Builder profile

Builder
J J CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53100019259
Status
New
Stage
Certificate Signed
Possession
October 2021
Construction
43.2% complete
Units sold
0 of 0

Similar projects in VIJAYNAGAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how VIJAYNAGAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.