VEDANT DEWELLS
by YOGIVALLABH BUILDERS AND DEVELOPERS
C S NO 6716B/15 C S NO 6716B/21, OLD KUPWAD ROAD, 416415
- Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Apr 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Where it is · C S NO 6716B/15 C S NO 6716B/21, OLD KUPWAD ROAD
Area guide
What it's like to buy in OLD KUPWAD ROAD
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P53100053582
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2027originally December 2025
- Construction
- 52.3% complete
- Units sold
- 6 of 18
Keep exploring
Where this project sits, who built it, and how OLD KUPWAD ROAD compares.
In OLD KUPWAD ROAD
The developer
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.