Under construction
VIMACO GULMOHAR CONDOMINIUM
MahaRERA P50300006416High risk
by ABBASALI AHTESHAM HUSAIN HAJI
SHEETA NO. 18-C, NAZUL PLOT NO. 1, Amravati (M Corp.), 444606
Post your property hereOwn or renting out a unit in VIMACO GULMOHAR CONDOMINIUM? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Amravati (M Corp.) come to you.
Jun 2022
Possession
9.1%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~1 yr. Originally promised Dec 2020, now proposed Jun 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 9.1%.
Satellite view of this address
Where it is · SHEETA NO. 18-C, NAZUL PLOT NO. 1, Amravati (M Corp.)
Promoter
Builder profile
ABBASALI AHTESHAM HUSAIN HAJI
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P50300006416
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2022originally December 2020
- Construction
- 9.1% complete
- Units sold
- 0 of 0
Similar projects in Amravati (M Corp.)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
UDAY NAGAR LAYOUT A
Amravati (M Corp.)Poss. October 2019
UDAY NAGAR LAYOUT D
Amravati (M Corp.)Poss. October 2019
UDAY PARK - LAYOUT C
Amravati (M Corp.)Poss. October 2019
UDAY NAGAR -LAYOUT B
Amravati (M Corp.)Poss. October 2019
GOVINDA CITY - 1
Amravati (M Corp.)Poss. March 2019
SHIVANAND HEIGHTS
Amravati (M Corp.)100% builtPoss. February 2023
RASHI TRINITY
Amravati (M Corp.)100% builtPoss. May 2018
Shri Radha Krishna Residency
Amravati (M Corp.)100% builtPoss. March 2019
Keep exploring
Where this project sits, who built it, and how Amravati (M Corp.) compares.
In Amravati (M Corp.)
The developer
Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.