Under construction

VIMACO GULMOHAR CONDOMINIUM

MahaRERA P50300006416High risk

by ABBASALI AHTESHAM HUSAIN HAJI

SHEETA NO. 18-C, NAZUL PLOT NO. 1, Amravati (M Corp.), 444606

Official record
Jun 2022
Possession
9.1%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2020, now proposed Jun 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 9.1%.
Satellite view of this address

Where it is · SHEETA NO. 18-C, NAZUL PLOT NO. 1, Amravati (M Corp.)

Promoter

Builder profile

Builder
ABBASALI AHTESHAM HUSAIN HAJI

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P50300006416
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally December 2020
Construction
9.1% complete
Units sold
0 of 0

Similar projects in Amravati (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Amravati (M Corp.) compares.

Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.