Under construction

VITHAI BUILDING A

MahaRERA P52800021724High risk

by SARITA CORPORATION

28,1155,1157,1158,1159, PALPENE, 415724

Official record
Jul 2026
Possession
81.8%
Built
0
Complaints
49
Units
High risk
  • Possession delayed ~4 yrs. Originally promised May 2022, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 81.8%.
Satellite view of this address

Where it is · 28,1155,1157,1158,1159, PALPENE

Area guide

What it's like to buy in PALPENE

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SARITA CORPORATION

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52800021724
Status
New
Stage
Certificate Signed
Possession
July 2026originally May 2022
Construction
81.8% complete
Units sold
13 of 49