High risk
  • Possession delayed ~4 yrs. Originally promised Jul 2022, now proposed Dec 2026 per the RERA filing.
  • 22 RERA complaints. 22 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · Gat No. 1043/2/2 Plot No. 1, Wai

Promoter

Builder profile

Builder
SHREEJI HABITAT LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52700004937
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally July 2022
Construction
50.5% complete
Units sold
0 of 0

Similar projects in Wai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Wai compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.