High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~7 yrs. Originally promised Mar 2022, now proposed Apr 2029 per the RERA filing.
Satellite view of this address

Where it is · GAT NO 915-B, Kawathe

Promoter

Builder profile

Builder
VIVID BUILDCOM

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SUNIL D BHAMARE

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52700013169
Status
Ongoing
Stage
Certificate Signed
Possession
April 2029originally March 2022
Construction
—
Units sold
7 of 77

Keep exploring

Where this project sits, who built it, and how Kawathe compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.