High risk
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 60.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2026 per the RERA filing.
Satellite view of this address

Where it is · D-225 AND D-226, OPP DY PATIL STADIUM

Area guide

What it's like to buy in OPP DY PATIL STADIUM

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Navi Mumbai (Vashi–Nerul)Mid-income

Planned-city order — wide roads, node markets, established social infra.

Growth drivers:
Atal Setu (MTHL), metro lines, the upcoming Navi Mumbai airport.
Who buys here:
Professionals wanting planned-city living with airport-corridor upside.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
DREAM APEX REALTIES LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
SOYUZ TALIB ARCHITECTS

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700025150
Status
New
Stage
Certificate Signed
Possession
April 2026
Construction
60.9% complete
Units sold
603 of 732

Keep exploring

Where this project sits, who built it, and how OPP DY PATIL STADIUM compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.