Delayed projects in Thane
1,593 MahaRERA-registered projects in Thane are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 1 of 8
- SUYOG8.6 yr overdueMADHAV BHALCHANDRA PARANJAPE · Kalyan, ThaneP51700010683· 81.8% built
- SHIV SHANKAR RESIDENCY8.6 yr overdueSAI GURUKRUPA CONSTRUCTION & DEVELOPERS · Thane, ThaneP51700005594· 81.8% built
- Centilia8.6 yr overdueAcme Housing India Private Limited · Thane (M Corp.), ThaneP51700010837· 54.5% built· 1 complaint
- DATTUSAI COMPLEX BUILDING NO 28.6 yr overdueSAIRAJ ENTERPRISES · DOMBIVLI, ThaneP51700013185· 90% built
- Rai Valley A B C Wing8.6 yr overdueRAI RESIDENCY Private Limited · Kalyan, ThaneP51700011390· 89.1% built
- Seawood Harmony8.6 yr overdueGeo Builders · Thane, ThaneP51700005814· 90.9% built
- vedant nakshatra ABC phase 18.6 yr overdueMOHAN HARDASMAL THARWANI · Badlapur (M Cl), ThaneP51700013039· 90.9% built
- SHIV VATIKA8.6 yr overdueSHIV ENTERPRISES · Ambarnath(M Cl), ThaneP51700011672· 90.9% built
- Trimity Ashwa8.6 yr overdueTrimity Constructions · Kasarwadavali, ThaneP51700007057· 72.7% built
- MOUNT VIEW8.6 yr overdueBALKRISHNA KASHINATH BHOIR · Ambarnath(M Cl), ThaneP51700011368· 90.9% built
- Madhumalti8.6 yr overdueDilip Madhukar Dalvi · Kalyan-Dombivali (M Corp.), ThaneP51700012542· 90.9% built· 4 complaints
- Sharvari Primero8.6 yr overdueSHARVARI REALTORS LLP · Kalyan, ThaneP51700000601· 9.8% built
- DHARTI HILLS8.6 yr overdueKRISHNA ENTERPRISES · Ambarnath(M Cl), ThaneP51700012074· 90.9% built
- Om Sai Residency8.6 yr overdueOm Sai Residency · Manda, ThaneP51700013426· 90.9% built
- SAI RAJ HEIGHTS8.6 yr overdueSHRI SAI DEVELOPERS · Ambarnath, ThaneP51700004223· 54.5% built
- Mangeshi Paradise - I8.6 yr overdueAnnapurna Universal · Kalyan-Dombivali (M Corp.), ThaneP51700010709· 86.4% built
- KANHA RESIDENCY8.6 yr overdueKANHA MOTIRAM KENE · Kalyan, ThaneP51700006676· 90% built
- SHREE HEIGHTS8.6 yr overdueSHREE DEVELOPERS · Kalyan, ThaneP51700010906· 90.9% built
- USHA KIRAN RESIDENCY WING E1 E2 E38.6 yr overdueSTALWART IMPEX PVT LTD · Badlapur (M Cl), ThaneP51700012135· 84.8% built
- UTKARSH8.6 yr overdueMADHAV BHALCHANDRA PARANJAPE · DOMBIVLI, ThaneP51700012558· 90.9% built
- POONAM ESTATE MHADA BLDG NO 8 AND 98.6 yr overdueRavi Developments · Mira-Bhayandar (M Corp.), ThaneP51700011797· 90.9% built
- OSIANS GARDEN8.6 yr overdueOSIAN DWELLINGS PRIVATE LIMITED · Bhiwandi, ThaneP51700006805· 48.4% built
- SAI ARCADE8.6 yr overdueSAI DEVELOPERS · Badlapur (M Cl), ThaneP51700009522· 90.9% built
- SWANAND TREO BUILDING NO 3 -SWAMI GANNAYAK8.6 yr overdueSWANAND HEIGHTS · BADLAPUR, ThaneP51700013459· 90.9% built
- SAINATH HEIGHTS8.6 yr overdueDESAI CONSTRUCTIONS · Ambarnath(M Cl), ThaneP51700008556· 45.5% built
- SIDHESHWAR COMPLEX BUILDING 1 A WING8.6 yr overdueADESHWAR ASSOCIATES · TITWALA, ThaneP51700011114· 90.9% built
- Aarya Heights8.6 yr overdueSHAILESH SHOBNATH MISHRA · Thane, ThaneP51700010776· 90.9% built
- MARUTI ASTHA8.6 yr overdueMARUTI HOMES · Badlapur (M Cl), ThaneP51700013850· 79.1% built
- VINAYAK KONDILKAR ARCADE8.6 yr overdueVINAYAK BUILDERS & DEVELOPERS · Badlapur (M Cl), ThaneP51700010372· 90.9% built
- SATGURUS SOLITAIRE8.6 yr overdueBUILDWELL LAND DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700004996· 98.2% built· 1 complaint
- VISHNU PLAZA8.6 yr overdueVISHNU DEVELOPERS · Ambivali Tarf Chon, ThaneP51700005866· 81.8% built
- LODHA FRESHIA WING A, B, C8.6 yr overdueLodha Developers Limited · Kalyan, ThaneP51700004667· 90.9% built
- NISARG8.6 yr overdueSHREE SAI UNITY BUILDERS AND DEVELOPERS · Badlapur (M Cl), ThaneP51700010273· 90.9% built
- SOHAM PLAZA8.6 yr overdueSAIBHAKTI BUILDERS · Titwala, ThaneP51700003435· 90.9% built
- Rosa Oasis Phase 38.6 yr overdueUma Enterprises · Thane, ThaneP51700006155· 90.9% built
- Basilia8.6 yr overdueAcme Housing India Private Limited · Thane (M Corp.), ThaneP51700010925· 54.5% built· 1 complaint
- AMRUTWANI COMPLEX D TYPE8.6 yr overdueStone House Developer · KALYAN, ThaneP51700012622· 90% built· 1 complaint
- CHINTAMANI HABITAT DAFFODILS TYPE F8.6 yr overdueJASHNANI CONSTRUCTION PRIVATE LIMITED · Shahapur (CT), ThaneP51700001557· 81.8% built
- SAWLARAM SRUSHTI8.6 yr overdueSHREE SAI BUILDERS AND DEVELOPERS · Kalyan, ThaneP51700002398· 73.1% built
- PALAVA - UNO H - O8.6 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000142· 78.2% built· 4 complaints
- Omkar Heights8.6 yr overdueSwati Enterprises · Manda, ThaneP51700000327· 90.9% built
- ASHTAVINAYAK AVENUE8.6 yr overdueAshtavinayak Infrastructure · Ambarnath(M Cl), ThaneP51700009467· 77.3% built
- SUDAMA GREENS8.6 yr overdueSACHIN SUDAM PATIL · Thane, ThaneP51700010295· 90.9% built
- INDRALOK HEIGHTS8.6 yr overdueINDRALOK CONSTRUCTION CO · Thane, ThaneP51700005737· 72.7% built
- SHANTI KUNJ8.6 yr overdueSHREYAS ENTERPRISES · Thane, ThaneP51700004964· 53.9% built
- AMI DARSHAN E WING8.6 yr overdueAAROHI DEVELOPMENT CORPORATION · Kalyan, ThaneP51700004410· 90.9% built
- PRATHAM HEIGHTS8.6 yr overduePRATHAM INFRASTRUCTURE · Thane, ThaneP51700008448· 41.8% built
- KULSWAMINI HEIGHTS8.6 yr overdueHARI OM DEVELOPERS · Kalyan, ThaneP51700005364· 89.4% built
- ASHAPURA BUILDERS AND DEVELOPERS8.6 yr overdueASHAPURA BUILDERS AND DEVELOPERS · Ambarnath(M Cl), ThaneP51700013043· 90.9% built
- Ramdev Villa8.6 yr overdueRamdev Villa · Thane, ThaneP51700006067· 90.9% built
- PALAVA LAKESIDE I TO O8.6 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000410· 78.2% built· 5 complaints
- OM SAI TOWERS8.6 yr overdueD A CONSTRUCTION · Ambarnath(M Cl), ThaneP51700011648· 44.5% built
- PALAVA - ELITE - A to J8.6 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000125· 78.2% built· 3 complaints
- SUCHIT SQUARE8.5 yr overdueIMPRESSIONS · Kalyan, ThaneP51700008664· 90.8% built
- Zubeda Imam Ahmed Bharmal Appartment8.5 yr overdueAAMIRBAHAUDDIN · BHIWANDI, ThaneP51700014694· 55.9% built
- SALASAR ASHISH8.4 yr overdueSALANGPUR REALTY · Thane, ThaneP51700011018· 90.9% built
- SADASHIV PURAM8.4 yr overdueSATYABHAMA DEVELOPERS · Ambarnath(M Cl), ThaneP51700010168· 90.9% built
- SMITAL AVENUE8.4 yr overdueD. L. BUILDERS PVT. LTD. · Mira-Bhayandar (M Corp.), ThaneP51700010363· 86.4% built
- TRITAN MEADOWS8.4 yr overdueTULIP REALTY · Thane, ThaneP51700002100· 74.2% built· 1 complaint
- Sadguru Residency8.4 yr overdueSADGURU INFRA · Ambarnath, ThaneP51700004161· 90.9% built
- Kalp City8.4 yr overdueKASATA HOME TECH · Badlapur (M Cl), ThaneP51700007780· 54.5% built
- SHREE MANGALMURTI8.4 yr overdueSHIVAM UNIVERSAL · Kalyan, ThaneP51700002559· 80% built
- Seven Eleven Residency8.4 yr overdueSeven Eleven Construction Private Limited · Mira-Bhayandar (M Corp.), ThaneP51700011597· 90.9% built
- SHIVKRUPA8.4 yr overdueANANT ARJUN MADHAVI · Thane, ThaneP51700013028· 36.4% built
- ADITYA VILLA8.4 yr overduePrashant Aditya Shukla · Ambarnath(M Cl), ThaneP51700005239· 81.8% built
- SHREE SAI DARSHAN8.4 yr overdueSHREE SIDDHIVINAYAK BUILDERS & DEVELOPERS · Kalyan-Dombivali (M Corp.), ThaneP51700011942· 90.9% built
- PADMALAXMI8.4 yr overdueKEDAR BHIKAJI BAPAT · Thane, ThaneP51700000815· 73.6% built
- MADHUMALTI APARTMENT B WING8.4 yr overdueSHREE DATTA ENTERPRISES · Belavli, ThaneP51700014710· 81.8% built
- SAI SHRUTI8.4 yr overduePINNACLE CONSTRUCTIONS · Badlapur (M Cl), ThaneP51700006060· 90.9% built
- POONAM ESTATE CL 2 BLG NO 1 2 38.4 yr overdueRavi Developments · MIRA ROAD EAST, ThaneP51700009072· 95.5% built
- SAMRUDDHI EVERGREENS-PHASE-4A8.4 yr overduePoddar Housing and Development Limited · Badlapur (M Cl), ThaneP51700009407· 78.2% built
- VASTU SQUARE8.4 yr overdueVASTU BUILDERS · Badlapur (M Cl), ThaneP51700009315· 72.7% built
- KRISHNA KUNJ8.4 yr overdueKRISHNA ASSOCIATES · Badlapur (M Cl), ThaneP51700011958· 81.8% built
- SARATHI RESIDENCY8.4 yr overdueSEEMA VIJAY NIKAM · Bhiwandi, ThaneP51700005507· 90.9% built
- A-2 MARIGOLD8.4 yr overdueMUKTA DEVELOPERS · Thane, ThaneP51700003734· 84.5% built
- TIRUPATI HIEGHTS8.4 yr overdueSHRI TIRUPATI REALTY · Bhiwandi, ThaneP51700006941· 79.1% built
- Atmaram Sadan8.4 yr overdueAditya Associates · Thane, ThaneP51700011909· 63.4% built
- Ramdev Vaayu8.4 yr overdueManoj Motaji Purohit · Thane, ThaneP51700010095· 82.7% built
- JAI SANTOSHI MATA HEIGHTS8.4 yr overdueRAJIV THAKUR & ASSOCIATES · DOMBIVLI, ThaneP51700012270· 77.3% built
- M/s. Shubham Karoti Complex Phase - I8.4 yr overdueM/s. Shubham Karoti Enterprises · Badlapur (M Cl), ThaneP51700005284· 65.9% built
- KRISHNA KUNJ8.4 yr overdueRAJ MANOHAR WADHWA · Badlapur (M Cl), ThaneP51700006536· 75% built
- B-1 Mukta Heights8.4 yr overduePRAVIN SAKHARAM PATIL · Thane, ThaneP51700010086· 76.4% built
- CHARMS HEIGHTS PHASE-I B1-B48.4 yr overdueCharms Developers · Titwala, ThaneP51700002055· 90.9% built· 2 complaints
- BHAKTI PARK B WING8.4 yr overdueBHAKTI CORPORATION · Badlapur (M Cl), ThaneP51700011425· 71.8% built· 1 complaint
- CHARMS PARADISE C WING8.4 yr overdueCharms Corporation · TITWALA EAST, ThaneP51700004417· 90.9% built
- Seven Eleven Regency8.4 yr overdueSeven Eleven Construction Private Limited · Mira-Bhayandar (M Corp.), ThaneP51700010338· 90.9% built
- Siddharth Apartment8.4 yr overdueRohan Gruh Nirman · Badlapur (M Cl), ThaneP51700013427· 60.9% built
- MAGNUM8.4 yr overdueJITESH KAMLESH PATEL · Thane, ThaneP51700006334· 90.9% built
- AYODHYA8.4 yr overdueAAUM CONSTRUCTIONS · Thane, ThaneP51700005917· 89.1% built
- Om Shrinivas Apartment8.4 yr overdueShriniwas Developers · Badlapur (M Cl), ThaneP51700013518· 64.5% built
- Asawari8.4 yr overdueAshish Waman Gole · Badlapur (M Cl), ThaneP51700009484· 52.3% built
- Trimurti Heights8.4 yr overdueTrimurti Construction Co · Thane, ThaneP51700009075· 88.2% built
- Prathamesh Towers8.4 yr overdueShivam Developers · Thane (M Corp.), ThaneP51700008600· 88.2% built
- SAI PANACH8.4 yr overduePANACH RELATORS · Bhiwandi, ThaneP51700012012· 90.9% built· 2 complaints
- PALAVA VIENTO A to D8.4 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000342· 81.8% built· 3 complaints
- VASTU SHILP8.4 yr overdueVASTU HOMES · Badlapur (M Cl), ThaneP51700013407· 72.7% built
- CHARMS MEADOWS PHASE I8.4 yr overdueCHARMS PRIDE · Asangaon (CT), ThaneP51700010110· 90.5% built· 3 complaints
- SAI NAND8.4 yr overdueJ J TECHNOCRATS · Thane, ThaneP51700003217· 90.9% built
- SHREE UMA SHANKAR APARTMENT8.4 yr overdueSHREE SAI AASHRAY DEVELOPERS · Badlapur (M Cl), ThaneP51700005680· 90.9% built
- ROHAN GRUH NIRMAN8.4 yr overdueM/s Rohan Development · Chavindra, ThaneP51700007592· 60.9% built
- ETERNAL AVENUE8.4 yr overdueMAGNUM LIFE SPACES · Badlapur (M Cl), ThaneP51700006365· 90% built
- CASA UNIVIS - CIELO D8.4 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700001153· 90.9% built
- PRECIOUS HARMONY8.4 yr overdueM/s Soham Construction · Badlapur (M Cl), ThaneP51700006810· 90.9% built
- SKYLINE-II-MHADA8.4 yr overdueUNIQUE SHANTI NEMINATH DEVELOPERS LLP · Thane, ThaneP51700004954· 96.5% built
- CHARMS PARK PHASE 18.4 yr overdueCharms Corporation · TITWALA EAST, ThaneP51700004476· 90.9% built
- PARIJAT CO-OPERATIVE HOUSING SOCIETY LIMITED PHASE 18.4 yr overdueROHRA CONSTRUCTIONS · Ambarnath, ThaneP51700008541· 71.4% built
- PADMAPRABHA CO OP HSG SOCIETY8.3 yr overdueSHREE MAHAVEER ENTERPRISES · SHIRGAON BADLAPUR, ThaneP51700015031· 90.9% built
- RATTAN GALAXY8.3 yr overdueRATTAN PROPERTIES AND PROJECTS PRIVATE LIMITED · Ambarnath, ThaneP51700003240· 83.6% built
- UMIYA ARCADE WING A AND B8.3 yr overdueUMIYA CONSTRUCTION COMPANY · Titwala, ThaneP51700002949· 60.9% built
- PALAVA VISTA A to D8.3 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000395· 81.8% built· 3 complaints
- THARWANI SOLITAIRE PHASE I8.3 yr overdueANIL HARDASMAL THARWANI · Kalyan, ThaneP51700005630· 60.4% built
- SARASWATI CASTLE8.3 yr overdueBHUMIKA DEVELOPERS · Kalyan, ThaneP51700004428· 75.9% built
- DHAVLGIRI8.3 yr overduePERFECT BUILDERS · Ambarnath(M Cl), ThaneP51700012227· 53.3% built
- THARWANI ARIANA PHASE II8.3 yr overdueANIL HARDASMAL THARWANI · Ambarnath, ThaneP51700006127· 51.8% built
- GAYATRI PARK8.3 yr overdueVIKRAM BUILDERS · Thane, ThaneP51700010528· filed Dec 2017 → now Apr 2018· 90.9% built· 1 complaint
- SHUBH AARAMBH8.3 yr overduePACIFIC CONSTRUCTION & DEVELOPERS · Badlapur (M Cl), ThaneP51700012478· 50% built
- Sai Crystal8.3 yr overdueShraddha Corporation · Ambarnath(M Cl), ThaneP51700012359· filed Dec 2017 → now Apr 2018· 90.9% built
- SHRADDHA HEIGHTS8.3 yr overdueSHRADDHA CONSTRUCTIONS · Thane, ThaneP51700008034· 39.5% built
- BALAJI HEIGHTS8.3 yr overdueSHREE BALAJI REALITY · Thane, ThaneP51700004645· 90.9% built
- walchand nagar - 28.3 yr overduePRAKASH HAMIRMAL JAIN · Thane, ThaneP51700009826· 56.4% built
- RAVI DARSHAN8.2 yr overdueRAVI DEVELOPERS · Badlapur (M Cl), ThaneP51700011461· 66.4% built
- NILGIRI8.2 yr overdueSHIVAM DEVELOPER · Ambarnath, ThaneP51700003872· 72.7% built
- SILICON TOWER8.2 yr overdueSHREE RADHAKRISHNA DEVELOPER · Ambarnath, ThaneP51700004184· 51.8% built
- OM SAI VIHAR8.2 yr overdueJai Mahalaxmi Enterprises · Manda, ThaneP51700003493· 87.3% built
- MOTIRAM PRIVILEGE8.2 yr overdueVANITA ENTERPRISES · Ambarnath, ThaneP51700003347· 90.9% built
- SAI KANISHK PHASE I8.2 yr overdueOm Sai Infra & Om Sai Group · Thane, ThaneP51700006847· filed Dec 2017 → now May 2018· 90% built· 11 complaints
- TROPICAL LAGOON - 4 -JACARANDA8.2 yr overdueSOHAM ESTATES · Thane, ThaneP51700008485· 64.1% built· 23 complaints
- ASTER A WING RUCHA VATIKA8.2 yr overdueMILAN HOUSING COMPLEX PVT. LTD. · Titwala, ThaneP51700005590· 60.5% built
- Parijat Plaza Type B8.2 yr overdueM/s Parijat Constructions · Badlapur (M Cl), ThaneP51700010993· 80% built
- NANDRAJ NAGARI TYPE E8.2 yr overdueSWARAJ DEVELOPERS · Badlapur (M Cl), ThaneP51700009908· 81.8% built
- ASHWA ANNEX8.2 yr overdueASHWAMEDH CONSTRUCTION · Thane, ThaneP51700002512· 90.9% built
- Anand Sagar Enclave8.2 yr overdueVPA Developers · Kalyan, ThaneP51700002701· 54.5% built
- BHARAT RESIDENCY8.2 yr overdueSHIVSAI BUILDERS & DEVELOPERS · KLAYAN, ThaneP51700010262· 51.4% built
- Gagangiri Arcade8.2 yr overdueAKRUTI ASSOCIATES · Kalyan, ThaneP51700003151· 84.8% built
- Shivkripa Residency8.2 yr overdueRohit Developers · Thane, ThaneP51700010093· 77.3% built
- OM SAVAI NIKETAN8.2 yr overdueSAGAR SUPER STRUCTURES PRIVATE LIMITED · BADLAPUR, ThaneP51700009373· 73.6% built
- KOOL BREEZE PHASE II8.2 yr overdueABHISHEK SHELTERS LTD · Badlapur (M Cl), ThaneP51700010400· 84.5% built
- LEENA APARTMENT8.2 yr overdueHeramb Developers · Ambarnath(M Cl), ThaneP51700012362· 50% built
- OM RISHIKESH CHS Ltd8.2 yr overdueRiddhi Siddhi Enterprises · Ambarnath, ThaneP51700005679· 87.3% built
- KRISHNA VIHAR8.2 yr overdueKRISHNA SPACE · Bhiwandi, ThaneP51700005020· 90.9% built
- NEPTUNE SWARAJYA SECTOR 1- A158.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700005260· 60.9% built
- RUBYANA RESIDENCY PHASE 18.1 yr overdueSUDHIR DAMODAR GHATNEKAR · Badlapur (M Cl), ThaneP51700006102· 86.4% built
- NEPTUNE SWARAJYA SECTOR 1-A138.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700010783· 60.6% built
- RAJ ESTATE8.1 yr overdueD.V.BUILDERS & DEVELOPERS PVT. LTD. · Thane, ThaneP51700001702· 90.9% built
- PALAVA LAGOONA A TO F8.1 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000124· 78.2% built· 2 complaints
- NEPTUNE SWARJAYA SECTOR 1- A188.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700011116· 58.8% built
- Neptune Swarajya Sector 1 - 1A8.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700011863· 57.8% built
- NEPTUNE SWARAJYA SECTOR 1-A58.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700010289· 59.2% built· 1 complaint
- SUDAMA ENCLAVE8.1 yr overdueRAI RESIDENCY Private Limited · Kalyan, ThaneP51700011514· 60% built
- AAI CHS LTD8.1 yr overdueKALASH DEVELOPERS · Kalyan, ThaneP51700003266· filed Dec 2017 → now Jun 2018· 90.5% built
- YOGI NIWAS8.1 yr overdueELITE INFRASTRUCTURE · Ambarnath, ThaneP51700002560· 52.3% built
- SHUBHTEJ8.1 yr overdueJITNAT CONSTRUCTIONS · Thane, ThaneP51700014486· 90.9% built
- MANJIRI HEIGHTS8.1 yr overdueYASH INFRASTRUCTURE · Kalyan, ThaneP51700012188· 78.2% built
- PALAVA - PASEO - D to H8.1 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000269· 81.3% built· 1 complaint
- NEPTUNE SWARAJYA SECTOR 1-A38.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700011861· 59.8% built
- PHOENIX AVENUE8.1 yr overduePHOENIX INFRASTRUCTURE AND DEVELOPERS · Gandhare, ThaneP51700012079· 68.6% built
- NEPTUNE SWARAJYA SECTOR 1- A168.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700007460· 58.1% built
- NEPTUNE SWARAJYA SECTOR 1- A178.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700011115· 59.5% built
- Hill Spring Phase 18.1 yr overdueVelocity · Thane West, ThaneP51700009218· 93.5% built· 1 complaint
- NEPTUNE SWARAJYA SECTOR 1-A28.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700011191· 61.3% built
- HORIZON CLASSIQUE-I8.1 yr overdueSACHIN ENTERPRISES · Thane, ThaneP51700006371· 84.1% built
- Regency Sarvam Phase - 98.1 yr overdueREGENCY NIRMAN LTD · Titwala, ThaneP51700007066· 88.6% built
- SAI RESIDENCY8.1 yr overdueKALPAVRUKSHA DEVELOPERS · Ambarnath(M Cl), ThaneP51700011113· filed Dec 2017 → now Jun 2018· 81.8% built
- SHREE SAI LEELA8.1 yr overdueSHREE SAI BUILDERS & DEVELOPERS · Ambarnath, ThaneP51700000149· 81.8% built
- Trinity Galaxy R1 and R48.1 yr overdueTrinity Developers · Badlapur (M Cl), ThaneP51700007348· 62.3% built
- OLIVE8.1 yr overdueDINSHA BUILDERS AND DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700008260· 56.8% built
- ADITYA ROYAL8.1 yr overduePrashant Aditya Shukla · Ambarnath(M Cl), ThaneP51700009847· 81.5% built· 3 complaints
- SWAROOP ORCHID8.1 yr overdueSWAROOP CONSTRUCTION · Badlapur (M Cl), ThaneP51700010451· 81.4% built
- NEELKANTH SPARKLE8.1 yr overdueNEELKANTH ENTERPRISES · Thane, ThaneP51700005915· 72.7% built
- AMMAR MEADOWS PHASE 28.1 yr overdueMEENAR ASSOCIATES · Thane, ThaneP51700011147· 87.3% built· 1 complaint
- MAYFAIR VISHWARAJA8.1 yr overdueMAYFAIR HOUSING PRIVATE LIMITED · Near Ganesh Mandir, ThaneP51700000001· 90.9% built
- MANGESHI CRYSTAL8.1 yr overdueMangesh Dashrath Gaikar · Kalyan, ThaneP51700009923· 90.9% built· 1 complaint
- Aditi Plaza8.1 yr overdueChintamani Construction · Ambarnath, ThaneP51700001865· 90.9% built
- SHREE PANCHAM8.1 yr overdueSHREE PANCHAM ASSOCIATES · Mira-Bhayandar (M Corp.), ThaneP51700011256· 80% built
- SWAMI SADAN8.1 yr overdueMAHESH NARAYAN SASE · Ambarnath, ThaneP51700013676· 36.8% built
- Om Vatika8.1 yr overdueOm Shiv Enterprises · Badlapur (M Cl), ThaneP51700009019· 90.9% built
- PATIL HILL VIEW8.1 yr overdueEKDANT DEVELOPERS · Badlapur (M Cl), ThaneP51700011266· 85.9% built
- SWAMI DHAM8.1 yr overdueSHREE AYYAPPA CONSTRUCTIONS · Ambarnath, ThaneP51700005616· 76.4% built
- Sunrise Glory - Phase I8.1 yr overdueSUNRISE LIFESPACES LLP · Thane, ThaneP51700008298· 90.9% built· 12 complaints
- AMAR ORCHID8.1 yr overdueAMAR REALTY · Kalyan, ThaneP51700002411· 90.9% built
- NEPTUNE SWARAJYA SECTOR 1- A148.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700009907· 57.5% built
- ASHAR MILLENNIA8.1 yr overdueMs ASHAR VENTURES · Thane, ThaneP51700007307· 81.8% built
- Panvelkar Homes - Phase II8.1 yr overdueOm Sai Constructions · Ambarnath, ThaneP51700000656· 90.9% built
- ISHWAR ENCLAVE8.1 yr overdueISHWAR ENTERPRISES · AMBARNATH, ThaneP51700014663· 59.1% built
- NIRMAL NAGARI8.1 yr overdueUNIQUE BUILDCORN BUILDERS AND DEVELOPERS · Thane, ThaneP51700007265· 60% built· 2 complaints
- SANGHVI VALLEY A1 A28.1 yr overdueSanghvi Premises Private Limited · Thane, ThaneP51700009615· 89.1% built
- NEPTUNE SWARAJYA SECTOR 1-A48.1 yr overdueNEPTUNE DEVELOPERS LIMITED · Kalyan-Dombivali (M Corp.), ThaneP51700009803· 59.6% built
- Krishna Kunj Residency8.1 yr overdueAshoka Infrastructure · Badlapur (M Cl), ThaneP51700008902· 76.4% built
- MANGESHI SANSKAR8.1 yr overdueMangesh Dashrath Gaikar · Kalyan, ThaneP51700008382· 90.9% built
- PATEL PLANET - JUPITER8.1 yr overdueDHANLAXMI DEVELOPERS · Ambarnath, ThaneP51700000352· 51.8% built
- DAISY GARDENS SURVEY NO 12 PHASE II8.1 yr overdueANKITA BUILDERS · Ambarnath, ThaneP51700009095· 89.1% built
- HORIZON HEIGHTS D8.1 yr overdueSHREENATH ENTERPRISES · Thane, ThaneP51700010444· 84.1% built
- PATEL RESIDENCY NX8.1 yr overdueNAVNIRMAN DEVELOPERS · Ambarnath, ThaneP51700000745· 46% built
- Shivnath Habitats8.1 yr overdueSHIVNATH DEVELOPER · Thane, ThaneP51700009343· 90.9% built· 12 complaints
- Arham Vatika8.1 yr overdueArham Enterprises · Badlapur (M Cl), ThaneP51700008943· 82.7% built
- Shivnath Sky City8.1 yr overdueSHIVNATH DEVELOPER · Thane, ThaneP51700008666· 89.5% built
- VAKRATUND8.1 yr overdueSHREE SIDDHI VINAYAK DEVELOPERS · Thane, ThaneP51700012072· 90.9% built
- UMA ASHISH B WING8.1 yr overduePARASIYA DEVELOPES · Ambarnath, ThaneP51700002434· 88.2% built
- Snehadeep Co-Operative Housing Society Ltd8.1 yr overdueJOSHI ENTERPRISES · Thane, ThaneP51700013473· filed Dec 2017 → now Jul 2018· 90.9% built· 4 complaints
- Hubtown Greenwoods B wing8.1 yr overdueHubtown Limited · Thane, ThaneP51700004458· 85.1% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.