Delayed projects in Nagpur
386 MahaRERA-registered projects in Nagpur are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 1 of 2
- Bloomdale Building 10 B9.2 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500008833· filed Jan 2019 → now May 2017· 90.9% built
- Shri Swami Puram Wing C and D8.6 yr overdueshri aappa swami infrastructure · Nagpur (M Corp.), NagpurP50500008250· 90.9% built
- LAXMIKESHAV APPARTMENT8.6 yr overdueANSH INFRA MAKERS · Nagpur (M Corp.), NagpurP50500011088· 88.6% built
- Shriram Niwas Yojna - ii8.6 yr overdueNavin Subhedar Nagari Sahakari Pat Sanstha Maryadit, Nagpur · NAGPUR, NagpurP50500013935· 78.2% built
- Dhanwantari Heights8.6 yr overdueGandhe Construction Company · Nagpur (M Corp.), NagpurP50500006079· 87.7% built
- DEVIPRABHA GAURAV8.6 yr overdueDEVIPRABHA BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500002678· 74.5% built
- Pyramid City 38.6 yr overduePyramid Ventures India Pvt Ltd · Pipla, NagpurP50500004416· 90.9% built
- Shri Swami Puram Wing E8.6 yr overdueshri aappa swami infrastructure · Nagpur (M Corp.), NagpurP50500004973· 90% built
- SHREE NARAYANA CLASSIC8.6 yr overdueSHREE LAXMI VENTURE PVT LTD · Umred (M Cl), NagpurP50500000583· 90.9% built
- Pyramid city 18.6 yr overduePyramid Arcades Pvt Ltd · Nagpur (M Corp.), NagpurP50500012106· 90.9% built
- SHRIKRISHNA APARTMENT8.6 yr overdueNITIN VITHOBA GIRHE · Nagpur (M Corp.), NagpurP50500012137· 90% built
- JP ENIGMA8.6 yr overdueJaiprakash Gurdasmal Khushalani · Nagpur (M Corp.), NagpurP50500013221· 90.9% built
- Gangwani Plaza8.6 yr overdueGangwani Constructions Pvt LtdAA · Nagpur (M Corp.), NagpurP50500011201· 85.9% built
- Construction of 14 Rowhouses at Waddhamna Nagpur8.6 yr overdueMHADA(Nagpur Board) · Waddhamna, NagpurP50500012638· 75.2% built
- SHRIKRISHNA ENCLAVE DUPLEX PHASE 18.6 yr overdueSHRIKRISHNA INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500002555· 88.6% built
- AATREYA REGENCY8.6 yr overdueHARSHALI ANOOP DESHPANDE · Wanadongri (CT), NagpurP50500003312· 55.3% built
- Construction of 20 MIG flats on S.No.42,60 at Nari, Nagpur8.4 yr overdueMHADA (Nagpur Board) · Nagpur (M Corp.), NagpurP50500006157· 90.9% built
- GAJANAN PALACE8.4 yr overdueSHREE GAJANAN BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500002858· 90.9% built
- George Developers ELITE8.4 yr overdueGeorge Developers · Nagpur (M Corp.), NagpurP50500010620· 89.1% built
- The Address8.4 yr overdueMAGNITON INFRA · khmala, NagpurP50500012771· 90.9% built· 1 complaint
- Bloomdale Building 048.4 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500006445· 90.9% built· 5 complaints
- VAIBHAV HEIGHTS8.4 yr overdueVAIBHAV WAREHOUSING · Butibori, NagpurP50500003832· 59.1% built
- ROYAL ARCADE8.4 yr overdueNATIONAL BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500008878· 81.8% built
- KHADGE ENCLAVE8.4 yr overdueWasudeo Wamanrao Khadgi · Nagpur (M Corp.), NagpurP50500014344· 54.5% built
- Pritam Apartment8.4 yr overdueC. S. T. S. Renu · Nagpur (M Corp.), NagpurP50500004788· 90.9% built
- NEEL VIHAR WING-B8.2 yr overdueNeel Gagan Developers · Nagpur (M Corp.), NagpurP50500008240· 90.9% built
- SANJIRI RESIDENCY8.2 yr overdueZUBAIR HAJI BASHIR ASHRAFI · Nagpur (M Corp.), NagpurP50500014322· 15.5% built· 1 complaint
- GRACE GILGAL8.2 yr overdueSHAJAN RAPPAI VARIKKASSERY · Nagpur (M Corp.), NagpurP50500006343· 84.1% built
- Aadhar Apartment8.2 yr overdueGIRDHAR DHARAMSIBHAI RATHOD · NAGPUR, NagpurP50500015627· 81.8% built
- KASTURI NAGAR8.2 yr overdueSKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD. · Gotal Panjari, NagpurP50500002773· 70.1% built
- SHALWAK ELITE8.1 yr overdueSHALWAK INFRABULLS · Nagpur (M Corp.), NagpurP50500010251· 90.9% built
- NAKSHATRA-I8.1 yr overdueNAKSHATRA INFRAVENTURE · Pipla, NagpurP50500004090· 70% built· 1 complaint
- S H TOWN8.1 yr overdueS P ASSOCIATES · Nagpur (M Corp.), NagpurP50500009890· 21.2% built
- PLATINUM GREEN8.1 yr overdueUNNATI HOMES INFRACON · Nagpur (M Corp.), NagpurP50500006086· filed Dec 2017 → now Jun 2018· 81.8% built
- SHREE MANSION8.1 yr overdueSACHIN ASHOK KHARE · AJNI, NagpurP50500014642· 90.9% built
- Neel Vihar Wing c8.1 yr overdueNeel Gagan Developers · Narsala, NagpurP50500003714· 89.5% built
- Pushkar Orchid Greens Phase I8.1 yr overduePushkar Homes Private Limited · Borkhedi, NagpurP50500006050· 59.8% built· 1 complaint
- MAHALAXMI PALACE-18.1 yr overdueVIJAYA VIJAY INGLE · Nagpur (M Corp.), NagpurP50500006859· 69.1% built
- AARNA - 28.1 yr overduePradeep Subhash Somani · Nagpur (M Corp.), NagpurP50500013847· 89.1% built
- Pyramid City 48.1 yr overduePyramid Ventures India Pvt.Ltd · Besa, NagpurP50500006837· 81.5% built· 1 complaint
- Construction of 240 T/S under LIG8.1 yr overdueMHADA(Nagpur Board) · Waddhamna, NagpurP50500000792· 81.8% built
- Construction of 42 MIG Ts at Surabardi S.No.20/1,20/28.1 yr overdueMHADA(Nagpur Board) · Surabardi, NagpurP50500000920· 67.3% built
- Construction of 29 HIG Bunglow at Waddhamna,Nagpur8.1 yr overdueMHADA(Nagpur Board) · Hingna, NagpurP50500000774· 72.9% built
- Construction of 320 flats under HIGHS at MHADA City Empress Mill No.-5, Subhash Road, Nagpur. Ph I8.1 yr overdueMHADA(Nagpur Board) · Nagpur (M Corp.), NagpurP50500012639· 90.9% built
- OM ATHARVA APARATMENT8.1 yr overdueSUDHIR BABURAO KALE · Godhani (Railway), NagpurP50500006831· 90.9% built
- MAHANANDA RESIDENCY8.1 yr overdueNITIN PRAMODRAO HANDE · Nagpur (M Corp.), NagpurP50500013993· 58.6% built
- Capitol Homes8.1 yr overdueAmbika Buildtech Private LImited · Bokhara, NagpurP50500007267· 90.9% built
- Shiv Elite Phase II8.1 yr overdueOm Shivam Buildcon Private Limited · Shankarpur, NagpurP50500007132· 89.1% built
- Shiv Elite Phase I8.1 yr overdueOm Shivam Buildcon Private Limited · Shankarpur, NagpurP50500009639· 89.1% built
- SIDDHIVINAYAK8.1 yr overdueSHREE GAJANAN DEVELOPERS · Nagpur (M Corp.), NagpurP50500007623· 38.2% built
- OM AARADHYA APARTMENT8.1 yr overdueINFINITI INFRAVENTURES · Godhani (Railway), NagpurP50500002860· 90.9% built
- VIGNESH VERETX8.0 yr overdueVIGNESH NIRMAN · Nagpur (M Corp.), NagpurP50500011674· 90.9% built
- ABHINAV RESIDENCY8.0 yr overdueNANAKCHAND R AGRAWAL · Nagpur (M Corp.), NagpurP50500002521· 54.9% built
- Bloomdale Duplex Home 37.9 yr overdueMahindra Bebanco Developers Limited · Kahpri, NagpurP50500007843· filed Jun 2018 → now Sept 2018· 81.8% built
- ATHARVA VILLAMENTS7.9 yr overdueATHARVA INFRASTRUCTURES · Pipla, NagpurP50500002215· 90.9% built
- ATHARVA CASTLE7.9 yr overdueATHARVA INFRASTRUCTURES · Pipla, NagpurP50500001987· 81.8% built
- GOVINDAM APARTMENTS7.8 yr overdueM/s. Paul Brothers · Kadbi chowk, NagpurP50500008210· 92.7% built
- Fortune Heights7.8 yr overdueShree Maa Mahalakshmi Infraventures Private Limited · Nagpur (M Corp.), NagpurP50500003586· 28.5% built
- GLORIOUS PLAZA III7.8 yr overdueDREAMLAND REAL ESTATE DEVELOPERS · Ghogali, NagpurP50500011363· 81.4% built
- LA REGALIA7.6 yr overdueRAGHAV LIFESPACES · Ramdaspeth, NagpurP50500004826· 75% built
- SOLITAIRE7.6 yr overdueKAPIL NANDKISHOR NATHANI · Nagpur (M Corp.), NagpurP50500012837· 81.8% built
- VIGNESH SQUARE7.6 yr overdueVIGNESH NIRMAN · Nagpur (M Corp.), NagpurP50500008258· 41.4% built
- KOASTAL APARTMENTS7.6 yr overdueSAIVAS BUILDCON · Nagpur (M Corp.), NagpurP50500004155· 90.9% built
- SAMRUDDHI APARTMENT7.6 yr overdueAMOL ABHIJEET KAMBLE · Nagpur (M Corp.), NagpurP50500011027· 70.5% built
- JP RADIANCE7.6 yr overdueJAGDISHPRASAD HANUMNMAL SHARMA · Hingna, NagpurP50500001509· filed Dec 2017 → now Dec 2018· 90.9% built
- Pushkar Govind and Narayan Apartment7.6 yr overduePushkar Homes Private Limited · Zinga Bai Takli, NagpurP50500005009· filed Dec 2017 → now Dec 2018· 72% built
- FIVE ELEMENTS-VAYU7.6 yr overdueLOKESH SATYAPRAKASH SHIVHARE · besa, NagpurP50500014883· 76.4% built
- MANORATH7.6 yr overdueSAFE GUARDS · Wagdara (536054), NagpurP50500007530· filed Dec 2017 → now Dec 2018· 90.9% built
- VAIBHAVLAXMI APPARTMENT7.6 yr overduePETHE BUILDERS AND DEVELOPERS PVT LTD · Nagpur (M Corp.), NagpurP50500012874· 81.8% built
- HONEY KARTIK TOWER7.6 yr overdueT KHANDWANI BUILDERS AND DEVELOPERS · lakadganj, NagpurP50500015286· 90.5% built
- ATHARVA NAGARI IV7.6 yr overdueATHARVA INFRASTRUCTURES · Pipla, NagpurP50500002049· 90.9% built
- VISHVA RUKHMA APARTMENT7.6 yr overdueSHREE GANESH CONSTRUCTION BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500012593· filed Dec 2017 → now Dec 2018· 89.1% built
- NANIKS ASHTAVINAYAK VRINDAVAN7.6 yr overdueNANIK ASSOCIATES · Nara, NagpurP50500013013· 90.9% built
- KHAIRI27.6 yr overdueRAKESH REAL ESTATE · Nagpur (M Corp.), NagpurP50500010077· 9.1% built
- HINGNA CITY7.6 yr overdueVIDARBHA BUILDERS · HINGNA BUS STOP, NagpurP50500004473· 77.3% built
- BALAJI ANANDAM7.6 yr overdueBALAJI BUILDCRAFT INFRA PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500006012· filed Dec 2017 → now Dec 2018· 90.9% built
- WEST COURT7.6 yr overdueJ D BUILDCON PVT LTD · Nagpur (M Corp.), NagpurP50500005895· filed Dec 2017 → now Dec 2018· 90.8% built
- VENU ENCLAVE7.6 yr overdueOM SAI BUILDER & DEVELOPERS · Nagpur (M Corp.), NagpurP50500010162· 81.8% built
- NIRMITI ELITE7.6 yr overdueNIRMITI BUILDERS · Nagpur (M Corp.), NagpurP50500007016· 90.9% built
- KONAARK LAKESHORE7.6 yr overdueIDA INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500006586· 90.9% built
- AVIGHNA VIHAR 27.6 yr overdueConcept Builders · Godhani (Railway), NagpurP50500012585· 52.7% built
- VAIBHAV HEIGHTS II7.6 yr overdueVAIBHAV WAREHOUSING · Butibori, NagpurP50500004136· 59.1% built
- MAA VAISHNAVI RESIDENCY - FLATS7.6 yr overdueMAA VAISHNAVI REAL ESTATE · Umred (M Cl), NagpurP50400002587· 90.9% built
- PRATIKSHA7.6 yr overdueIVSS INFRASTRUCTURES · SUGAT NAGAR, NagpurP50500012077· 66.8% built
- RAMKRISHNA NAGARI7.6 yr overdueRAMKRISHNA DEVELOPERS · Narsala, NagpurP50500006674· filed Dec 2017 → now Dec 2018· 79.1% built
- AKSHAY ARCADE7.6 yr overdueAKSHAY CONSTRUCTIONS & BUILDERS · Godhani (Railway), NagpurP50500009703· 90.9% built
- SHIVAM PARK7.6 yr overdueSAMBHAV INFRA · Shankarpur, NagpurP50500002280· 86.4% built
- SANIKA VIHAR7.4 yr overdueANIL RAMDAS UKEY · Bhilgaon, NagpurP50500002354· 44.1% built
- SHREE RIDDHIE SIDDHIE APARTMENT7.4 yr overdueSWATI ASHUTOSH NAIK · Nagpur (M Corp.), NagpurP50500014260· 74.1% built
- LAXMI NARAYAN RESIDENCY7.4 yr overdueSUDARSHAN LAND AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500001582· 75% built
- SHREE CHANDRIKA MANSION7.4 yr overdueSACHIN ASHOK KHARE · LAXMINAGAR, NagpurP50500014716· 79.5% built
- Amrit Kalash7.4 yr overdueRaghukul Constructions Private Limited · Nagpur (M Corp.), NagpurP50500001929· 90.9% built
- Meher Shelter7.4 yr overdueRajvaibhav Infra · Nagpur (M Corp.), NagpurP50500008418· 90.9% built
- JP NAKSHTRA 1B7.4 yr overdueJAGDISHPRASAD HANUMNMAL SHARMA · Hingna, NagpurP50500002283· filed Mar 2018 → now Mar 2019· 72.7% built
- PRIME 97.4 yr overdueM/S. IMPRESSA CENTRAL · Dharampeth, NagpurP50500015201· 63.2% built
- Tulip7.4 yr overdueLEVERAGE INFRASTRUCTURES PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500001330· 90.6% built· 1 complaint
- JP NAKSHTRA 3B7.4 yr overdueJAGDISHPRASAD HANUMNMAL SHARMA · Hingna, NagpurP50500001703· filed Mar 2018 → now Mar 2019· 72.7% built
- AMALTAS7.4 yr overdueNOVELLUS INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500005633· filed Mar 2018 → now Mar 2019· 90.9% built· 2 complaints
- aarti empire7.4 yr overdueG N CONSTRUCTION · Nagpur (M Corp.), NagpurP50500006514· 41.8% built
- HIBISCUS GARDEN7.4 yr overdueURICH GRACE INFRASTRUCTURE PVT LTD · Gawasi Manapur, NagpurP50500012509· 39.5% built
- OLIVE SILLARI7.4 yr overdueCHANDRAPAL NATHUSAO CHOUKASEY · Nagpur (M Corp.), NagpurP50500012737· 72.1% built
- Ram Ranjan Apartments7.4 yr overdueRavindra Ramchandra Sangitrao · Nagpur (M Corp.), NagpurP50500012701· 54.3% built
- KRISHNA GANGA RESIDENCY7.4 yr overdueNIRMAL DEVELOPERS AND BUILDERS · Nagpur (M Corp.), NagpurP50500013591· 86.8% built
- EKDANT ENCLAVE7.4 yr overdueSiddhivinayak Properties · Nagpur (M Corp.), NagpurP50500014264· 60% built
- Bhalchandra Apartment7.4 yr overdueSiddhivinayak Properties · Nagpur (M Corp.), NagpurP50500014197· 90.9% built
- MAHALAXMI PALACE-27.4 yr overdueVIJAYA VIJAY INGLE · Nagpur (M Corp.), NagpurP50500010562· 38.2% built
- K-SQUARE APARTMENTS7.4 yr overdueANKIT CONSTRUCTION · Nagpur (M Corp.), NagpurP50500003259· 90.9% built· 36 complaints
- SHIVARPAN7.4 yr overdueRaghuveer Constructions · Nagpur (M Corp.), NagpurP50500001454· filed Mar 2018 → now Mar 2019· 90.9% built
- RANA BUSINESS COMPLEX7.4 yr overdueRANA INFRA · Nagpur (M Corp.), NagpurP50500007730· 27.7% built
- GANARAYA HEIGHTS-3 CONDOMINIUM7.4 yr overduePINNACLE BUILDCON · Nagpur (M Corp.), NagpurP50500013852· 11.6% built
- ROSE GARDEN7.4 yr overdueURICH GRACE INFRASTRUCTURE PVT LTD · Rui, NagpurP50500003460· 47.9% built
- BALAJI APARTMENTS7.4 yr overdueSMITA MUKUND VAIDYA · Nagpur (M Corp.), NagpurP50500002892· 47.7% built
- Royal Crest7.4 yr overdueNavabharat Infraventures Ltd. · Nagpur (M Corp.), NagpurP50500001369· 93.8% built· 1 complaint
- SANKALP ENCLAVE7.4 yr overdueM/S. N.K. ASSOCIATES · Wadi, NagpurP50500012658· 50% built
- SAI SANKUL7.3 yr overdueADITYA DEVELOPERS · MAUZA BORGAON, NagpurP50500020622· 90.9% built
- SHRI RAM KUNJ7.3 yr overdueRAI UDYOG LIMITED · LAKADGANJ, NagpurP50500016003· 95.5% built· 2 complaints
- PETALS7.3 yr overdueJD BUILDCON PVT LTD & SHRIKA DEVELOPERS PVT LTD · SHIVAJI NAGAR, NagpurP50500001914· 62.3% built
- LAXMIPATI TOWER7.2 yr overdueSBM DEVELOPERS · MOUDA, NagpurP50500015456· 72.3% built
- AVISHKAR RESIDENCY7.2 yr overdueSHREE DYC REALITIES PVT. LTD. · Nagpur (M Corp.), NagpurP50500001173· 47.5% built
- PEBBLES 57.1 yr overdueSPACE INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500012361· 85.9% built
- Rachana Madhukosh Wing C7.1 yr overdueRachana construction Co. (Nagpur) Pvt. Ltd. · Bhamti, NagpurP50500015593· 90.9% built
- SHREE DATTA NIWARA7.1 yr overdueTHE HOME MAKERS · Nagpur (M Corp.), NagpurP50500008983· filed Jun 2018 → now Jun 2019· 90.9% built
- SHREE RADHE COMPLEX7.1 yr overdueSHRIKRUSHNA DEVELOPERS · Nagpur (M Corp.), NagpurP50500006951· filed Jun 2018 → now Jun 2019· 81.8% built
- MAHALAXMI SANYOG PARK7.1 yr overdueMAHALAXMI BUILDERS AND DEVELOPERS · Besa, NagpurP50500006225· 71.7% built
- Shiv Elite Phase III7.1 yr overdueOm Shivam Buildcon Private Limited · Shankarpur, NagpurP50500005732· 89.1% built
- RADHE GREENS7.1 yr overdueHBK Infrastructures · Isasani (CT), NagpurP50500006587· filed Jul 2018 → now Jul 2019· 40.9% built
- MORNING GLORY7.1 yr overdueSPACE INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500010141· 90.9% built
- SUPREME PLAZA7.1 yr overdueSUPREME URBAN REALITIES PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500002753· 84.5% built
- CANAL HEIGHTS7.1 yr overdueNAVNIT STAR REALTY LLP · Nagpur (M Corp.), NagpurP50500006199· 69.5% built
- ANANT APARTMENT7.0 yr overdueSHASHIKANT MANOHAR DEO · Nagpur (M Corp.), NagpurP50500013588· 63.6% built
- Siddhivinayak Appartment7.0 yr overdueVijay Construction & Developers · Beltarodi, NagpurP50500001612· 73.3% built
- LIVIANO 27.0 yr overdueSPACE INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500010526· 67.3% built
- KASTURI SQUARE7.0 yr overdueSKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD. · Gotal Panjari, NagpurP50500008255· 57.3% built
- MAXX ELITE6.9 yr overdueMAXX BUILDER AND DEVELOPERS · harihar nagar, NagpurP50500013910· 73.3% built
- SDPL Aashray Dabha6.9 yr overdueSANDEEP DWELLERS PVT. LTD. · Dabha, NagpurP50500014329· 88.3% built
- KARTIK PLAZA6.9 yr overdueSUBHASH YUVRAJ MANMODE · ZINGABAI TAKLI, NagpurP50500015522· 40% built
- NECTAR RESIDENCY-II6.9 yr overdueJACKPOT DEALER PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500015022· 44.5% built
- ATHARVA FORTUNE6.9 yr overdueATHARVA INFRASTRUCTURES · Pipla, NagpurP50500002140· 90.9% built
- PYRAMID CITY 56.9 yr overduePYRAMID ARCADES PVT LTD · Pipla, NagpurP50500005437· filed Sept 2018 → now Sept 2019· 89.1% built· 1 complaint
- Rachana Sahira Wing A6.8 yr overdueRachana construction Co. (Nagpur) Pvt. Ltd. · Nagpur (M Corp.), NagpurP50500001307· filed Oct 2018 → now Oct 2019· 90.9% built· 1 complaint
- LANDMARK APARTMENT6.8 yr overdueSAND N STEEL · INDIAN, NagpurP50500014017· 4.5% built
- Bloomdale Row House 56.7 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500007925· filed Nov 2018 → now Nov 2019· 81.8% built
- Bloomdale Row House 66.7 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500007914· filed Nov 2018 → now Nov 2019· 81.8% built
- SHRI EKDANT ENCLAVE6.6 yr overdueMoreshwar Narayanrao Bhagat · Nagpur (M Corp.), NagpurP50500013928· 72.7% built
- JAYRAM RESIDENCY6.6 yr overdueJAYRAM BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500014242· 55.4% built
- BELLA VISTA6.6 yr overdueLAXMI KESHAV CONSTRUCTIONS AND SHRIKA DEVELOPERS PRIVATE LIMITED · Nagpur, NagpurP50500005466· 90.9% built· 1 complaint
- SHRIRAM TOWER6.6 yr overdueSUDHASHRI INFRACON · Nagpur (M Corp.), NagpurP50500012525· 90.9% built
- AFFORDABLE HOUSING PROPOSED ON KH.NO.54,CITY SURVEY NO.173 LAYOUT PLAN NEAR SHESHNAGAR.6.6 yr overdueNagpur Improvement Trust · SHESHNAGAR, NagpurP50500017530· 58.7% built
- Diamond One6.6 yr overdueDiamond Estate Builders & Developers · Nagpur (M Corp.), NagpurP50500001314· 81.8% built
- THE VIDARBHA PREMIER SAHANIWAS CHIKHALI KHURD NAGPUR6.6 yr overduePRAKASH NARAYANRAO RAOLE · VITTHAL NAGAR, NagpurP50500012223· filed Dec 2018 → now Dec 2019· 72.7% built
- IMPRESSA SKY HOMES6.6 yr overdueIMPRESSA REALTORS · MANKAPUR, NagpurP50500010028· 90.9% built
- TRILIUM6.6 yr overdueTRIF REAL ESTATE AND DEVELOPMENT LTD · Nagpur (M Corp.), NagpurP50500012878· 77.7% built
- WHITE PEARL6.6 yr overdueS S SHRIYA INFRASTRUCTURES · Nagpur (M Corp.), NagpurP50500010689· 11.6% built
- GREENFIELD 1 WING D6.6 yr overdueL G DEVELOPERS AND BUILDERS · Wanadongri, NagpurP50500009629· 90.9% built
- Bloomdale Duplex Home 46.6 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500007215· filed Dec 2018 → now Dec 2019· 81.8% built
- Amrit Sarita6.6 yr overdueRaghukul Constructions Private Limited · Nagpur (M Corp.), NagpurP50500001628· 81.8% built
- Techops Glory6.6 yr overdueTechops Infrastructure Pvt. Ltd. · Nagpur (M Corp.), NagpurP50500010692· 90% built
- BALAJI CORPORATE PARK6.6 yr overdueBALAJI BUILDCRAFT INFRA PRIVATE LIMITED · PRATAP NAGAR, NagpurP50500016644· 81.8% built
- BAITUS SALEHEEN6.6 yr overdueRainbow Constructions · SHANTINAGAR, NagpurP50500016107· 53.2% built
- VEDANT EMERALD PHASE 26.6 yr overdueNANIS BUILDCON PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500012141· 82.7% built
- SDPL Aashray Wanjara6.6 yr overdueSANDEEP DWELLERS PVT. LTD. · Wanjara, NagpurP50500013707· 90.9% built
- Vedaarya Homes6.6 yr overdueAdditya Infrastructure · Borkhedi, NagpurP50500003103· filed Dec 2018 → now Dec 2019· 90.9% built
- OM AADITYA APARTMENT6.6 yr overdueSUDHIR BABURAO KALE · GODHNI (RAILWAY), NagpurP50500015166· 90.9% built
- IMPRESSA GLORY HOMES6.6 yr overdueIMPRESSA VENTURES · NAGPUR, NagpurP50500006214· 90.9% built
- Radhe Govind Niwas6.6 yr overdueSHRIVARI PROPERTIES · Bajaj Nagar, NagpurP50500016170· 61.8% built
- VEDANT PERIDOT6.6 yr overdueNANIS BUILDCON PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500009166· 84.5% built
- GURU BRAMHA APARTMENT6.6 yr overdueM/s MAHARANA'S BUILDERS,DEVELOPERS AND ENGINEERS · Telangkhedi, NagpurP50500005639· 81.8% built
- Bloomdale Building 10 A6.6 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500007997· filed Jan 2019 → now Jan 2020· 90.9% built
- GREEN VIEW RESIDENCY6.6 yr overdueN K ASSOCIATES · BORGAON, NagpurP50500015333· 38.6% built
- Anoushka Gardens6.6 yr overdueRaghav Construction · Nagpur (M Corp.), NagpurP50500001804· 36.9% built
- BALKRISHNA APARTMENT6.5 yr overdueVENKAT BALKRISHNARAO BHATGARE · Nagpur (M Corp.), NagpurP50500010628· filed Feb 2019 → now Feb 2020· 55.1% built
- Govind Enclave6.5 yr overdueArun Wamanrao Khadgi · ., NagpurP50500013663· filed Feb 2018 → now Feb 2020· 80% built
- MAHADEV TOWER6.1 yr overdueMAHADEV MARKEING COMPANY · Nagpur (M Corp.), NagpurP50500013512· filed Jul 2018 → now Jul 2020· 90.9% built· 1 complaint
- ASTER5.9 yr overdueLEVERAGE INFRASTRUCTURES PRIVATE LIMITED · Bokhara, NagpurP50500001906· 86.4% built
- EARTH HEIGHTS I5.9 yr overdueEARTH INFRA · 13/14,NEW AMAR NAGAR, NagpurP50500016144· 90.9% built· 1 complaint
- Bloomdale Building 085.9 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500008536· filed Mar 2019 → now Sept 2020· 90.9% built· 4 complaints
- AASRA5.9 yr overdueIMPRESSA LAXMI · NAGPUR, NagpurP50500013844· 90.9% built· 1 complaint
- GALAXY MANSION VII5.9 yr overdueGALAXY ASSOCIATES · Beltarodi, NagpurP50500014357· 90.9% built
- IT-PARK5.9 yr overdueVIDARBHA INFOTECH PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500007181· 48.3% built
- TIRUPATI ENCLAVE5.9 yr overdueEKALAWYA WASEKAR & OTHERONE · Nagpur (M Corp.), NagpurP50500007836· 81.8% built
- Santoshi Apartment5.9 yr overdueKavita Jayendra Ahirkar · Layout of Vidharbha Housing Construciton Workers Association, NagpurP50500015746· 81.8% built
- CASA LOTUS5.9 yr overdueR. C. CON ASSOCIATES JV · Wanadongri, NagpurP50500002363· filed Dec 2019 → now Sept 2020· 90.9% built
- Shree Durga Apartment5.9 yr overdueMittal Developers · Nagpur (M Corp.), NagpurP50500001801· 72.7% built· 1 complaint
- Bloomdale Building 095.9 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500006483· filed Mar 2019 → now Sept 2020· 90.9% built· 2 complaints
- Orchid Crown5.9 yr overdueLandmarks Orchid Homes Infraventures · Somalwada, NagpurP50500015614· 82.7% built
- CHANDRA VITHOBA HEIGHTS5.8 yr overdueOM SAI RAM INFRAVENTURE · Jamtha, NagpurP50500014247· filed Dec 2018 → now Oct 2020· 38.2% built
- VIDARBHA PREMIER NAGRI PHASE 3 KALMESHWAR5.8 yr overduePRAKASH NARAYANRAO RAOLE · KALMESHWAR, NagpurP50500010477· filed Dec 2018 → now Oct 2020· 78.2% built
- VIDARBHA PREMIER SAHANIWAS JAITALA.NAGPUR5.8 yr overduePRAKASH NARAYANRAO RAOLE · JAITALA, NagpurP50500011968· filed Dec 2018 → now Oct 2020· 90.9% built
- MAPLE ENCLAVE5.8 yr overdueVINOD RAMASHRY TRIPATHI · Wagdara (536054), NagpurP50500013298· filed Dec 2018 → now Oct 2020· 90.5% built
- MEGHDOOT ENCLAVE5.8 yr overdueRAGHAV ASSOCIATES · HUDKESHWAR, NagpurP50500006571· filed Dec 2018 → now Oct 2020· 83.1% built
- ROYAL RESIDENCY5.7 yr overdueDESIGN DEVELOPERS PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500000348· 90.9% built
- PRABHA CITY5.6 yr overdueRUPALI GHARDE · Pawangaon, NagpurP50500012752· 72.9% built
- SHREEYOGIRAJ ASHISH5.6 yr overdueSHREEYOGIRAJ HOMEMAKERS PRIVATE LIMITED · LAXMINAGAR, NagpurP50500014519· 34.5% built
- SHRIRAM PLAZA II5.6 yr overdueSHRIRAM SM ASSOCIATES BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500013510· filed Jul 2018 → now Dec 2020· 41.8% built
- Balaji Sanyog5.6 yr overdueSanyog Construction Co. · Besa, NagpurP50500004586· 90.9% built
- SHRIRAM SAHANIWAS5.6 yr overdueHIMALAYA DWELLERS PRIVATE LIMITED · BOREGAON RINGROAD SQUARE, NagpurP50500000638· 89.1% built
- anupama pearl regency5.6 yr overduejarry profit · Nagpur (M Corp.), NagpurP50500004233· 90.9% built
- Shiv Elite Phase IV5.6 yr overdueOm Shivam Buildcon Private Limited · Shankarpur, NagpurP50500009553· 90.8% built
- Bloomdale Row House 75.6 yr overdueMahindra Bebanco Developers Limited · Kahpri, NagpurP50500008161· filed Jul 2019 → now Jan 2021· 80.9% built
- Shiv Brighton Phase I5.6 yr overdueOm Shivam Buildcon Private Limited · Panjari farm, NagpurP50500006203· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.