Delayed projects in Raigarh
1,018 MahaRERA-registered projects in Raigarh are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 1 of 6
- SIDDHIVINAYAK HOMES8.6 yr overdueRAM VASDEV BATHIJA · Panvel, RaigarhP52000010894· 90.9% built
- EKDANTA CHHAYA8.6 yr overdueEkdanta Realtors · Bhuwaneshwar (CT), RaigarhP52000011877· 81.8% built
- GOLD CREST ENCLAVE8.6 yr overdueGOLDCREST BUILDERS & DEVELOPERS · Ulawe, RaigarhP52000009124· 88.2% built· 1 complaint
- SADHGURU8.6 yr overdueSHREEDEV ENTERPRISE · Ulawe, RaigarhP52000007337· 90.9% built
- SAI PEARL8.6 yr overdueSHREE DEVELOPERS · Karanjade, RaigarhP52000003239· 99.1% built
- SIDDHIVINAYAK PHASE 18.6 yr overdueGOKA ENGINEERING COMPANY PVT LTD · Warachiwadi, RaigarhP52000002530· 81.2% built
- MAPLE VILLA8.6 yr overdueAVACHAR BEACHARA BHATHI · Karanjade, RaigarhP52000009935· 90.9% built
- R N AVENUE8.6 yr overdueR N BUILDERS · Karanjade, RaigarhP52000003363· 90.9% built
- PLATINUM LIVIANO8.6 yr overduePLATINUM LIFESTYLE LLP · Panvel, RaigarhP52000005906· 90.9% built
- JINETE PARK8.6 yr overdueNAVKAR ENTERPRISES · Ulawe, RaigarhP52000007826· 68.5% built
- SHREE KRUPA8.6 yr overdueSHREE GANESH DEVELOPERS · Ulawe, RaigarhP52000013063· 72.7% built
- Ozone Residency B wing8.6 yr overduewestcoastrealty · Alibag, RaigarhP52000007382· 90.9% built
- ASHLESHA8.6 yr overdueSHARAD MAHADEO SARAVADE · Panvel, RaigarhP52000014125· 78.2% built
- RASIKA BUILDERS AND DEVELOPERS NERAL8.6 yr overdueRAVINDRA RAMCHANDRA BHOIR · Mamdapur, RaigarhP52000005131· 90.9% built
- SKYLINE HEIGHTS8.6 yr overduePEARL PROPERTIES · Karanjade, RaigarhP52000008413· 90.9% built
- SAPPHIRE BLISS8.6 yr overdueRAJESH BIJLANI · Panvel, RaigarhP52000009941· 72.7% built
- JUNCTION 4068.6 yr overdueMISHAL REALTY · Panvel, RaigarhP52000011771· 81.8% built
- SHRI GANESH RESIDENCY8.6 yr overdueSHRI GANESH DEVELOPERS · Ulawe, RaigarhP52000002170· 90.9% built
- HIRAYS TULIP8.6 yr overdueJAGANNATH DASHARATH HIRAY · Ulawe, RaigarhP52000011105· 90.9% built
- RAJ AMBAR8.6 yr overdueRAJ INFRA DEVELOPERS · Karanjade, RaigarhP52000001295· 90.9% built
- SHUBHA8.6 yr overdueENVISION INFRA · Khalapur, RaigarhP52000002697· 81.8% built
- SOHAM RESIDENCY8.6 yr overdueVISHAL DUTT · Panvel, RaigarhP52000004661· 96.8% built
- OM DATTAPRASAD CO OP HSG SOCIETY LTD8.6 yr overdueKIRAN NARAYAN MANORE · Panvel, RaigarhP52000003980· 94.1% built
- LOVE SPRING8.6 yr overdueAPEX BUILDTECH · Panvel, RaigarhP52000009108· 90.9% built
- GOLD VALLEY KONKAN8.6 yr overdueGOKA ENGINEERING CO PVT LTD · Mangaon, RaigarhP52000005331· 78.2% built· 1 complaint
- BHOSALE CARNATION8.6 yr overdueLEENA ARJUN GARAD · Ulawe, RaigarhP52000012884· 75.5% built
- SHREE RAM KALPANA8.6 yr overdueNEELKANTH ASSOCIATES · Panvel, RaigarhP52000013551· 90.9% built
- Sai Samartha Blessings8.6 yr overdueShree Sai Samartha Developers · Panvel, RaigarhP52000011613· 81.8% built
- Balaji Heights8.6 yr overdueBalaji Adventures · Panvel, RaigarhP52000003788· 75.1% built
- SHAGUN APARTMENT8.6 yr overdueSHREE VARAD VINAYAK DEVELOPERS · Taloje Panchnad, RaigarhP52000013848· 66.4% built
- IMAGE8.6 yr overdueIMAGE A AUTHENTICITY OF DREAM · Ulawe, RaigarhP52000009300· 45.5% built
- Shelter Corner8.6 yr overdueRabbani Shamsuddin khan · Panvel, RaigarhP52000010366· 90.9% built
- MAHAVIR VILLA8.6 yr overdueVIPUL BHIMSHI SATRA · Panvel, RaigarhP52000004151· 87.3% built
- SHANTI NIKETAN8.6 yr overdueSHREE SAIDATT DEVELOPERS · Karanjade, RaigarhP52000012693· 90.9% built
- Garva Residency-C38.6 yr overdueGarva Developers Pvt Ltd · Warse, RaigarhP52000006946· 70% built
- SHUBHAM RESIDENCY8.6 yr overduePOTE SONS BUILDERS & DEVELOPERS · Karanjade, RaigarhP52000006093· 90.9% built
- SIDDHI BELEZZA8.6 yr overdueSIDDHITAPASWI BUILDTECH · Panvel, RaigarhP52000010558· 90.9% built
- BANKERS TOWER CO OP HSG SO8.6 yr overdueBANKERS TOWER CHS · Bamandongri, RaigarhP52000010516· 70% built
- Welkin Star8.6 yr overdueWELKIN DEVELOPERS · ULAWE, RaigarhP52000011234· 90.9% built
- SIDDHIVINAYAK JEWEL8.6 yr overdueSHRIKANT DHONDU HINDALKAR · Panvel, RaigarhP52000007395· 87.1% built
- ZAHRAA RESIDENCY8.6 yr overdueAZ REALTY LLP · Ulawe, RaigarhP52000004154· 76.8% built
- NEXUS HEIGHTS8.6 yr overdueM/S NEXUS REALTY · Taloje Panchnad, RaigarhP52000013983· 97.7% built
- Tulsi Sapphire8.6 yr overdueSHREE MAHAVIR DEVELOPERS · Ulawe, RaigarhP52000001395· 90.9% built
- NEELKANTH PRAJAKT8.6 yr overdueNEELKANTH CONSTRUCTIONS · OLD THANA NAKA ROAD, RaigarhP52000013574· 90.9% built
- VIGHNAHAR SUDAMA8.6 yr overdueMAHESH SUDAM PATIL · Pen (M Cl), RaigarhP52000014318· 90.9% built
- BHOSALE ORCHID8.6 yr overdueBHOSALE LAND DEVELOPERS · Ulawe, RaigarhP52000012681· 90% built
- ANIRUDDHA ASTHA8.6 yr overdueYOGI ENTERPRISES · Panvel, RaigarhP52000007715· 90.9% built
- VIGHNAHAR RESIDENCY8.6 yr overdueNAFIAH DEVELOPERS · Karanjade, RaigarhP52000004761· 90% built· 2 complaints
- THE ATLANTIS8.6 yr overdueDHANYA CONSTRUCTION · Ulawe, RaigarhP52000009741· 89.1% built
- ADINATH AURA8.6 yr overdueSHREE RIDDHI SIDDHI CONSTRUCTIONS · Panvel, RaigarhP51700007724· 90.9% built
- CROWN EUREKA8.6 yr overdueASGARALI HUSEINIBHAI CONTRACTOR · Panvel, RaigarhP52000012036· 90.9% built
- Garva Residency-B28.6 yr overdueGarva Developers Pvt Ltd · Warse, RaigarhP52000004481· 43.2% built
- Gold Coast8.6 yr overdueA SQUARE CONSTRUCTION · Alibag, RaigarhP51800002294· 90.9% built
- ROYAL BELLEZA8.6 yr overdueANANDKUMAR HARIDAS SONI · Ulawe, RaigarhP52000006588· 90.9% built
- SAI AANGAN8.6 yr overdueSAIJYOTBUILDERS&DEVELOPERS · Ulawe, RaigarhP52000003244· 90.9% built
- SHREEJI RESIDENCY8.6 yr overdueSHREE HARI DEVELOPER · Panvel, RaigarhP52000004504· 90.9% built
- SAI DURGA HILLS8.5 yr overdueSAI DURGA DEVELOPERS · Bopele, RaigarhP52000003811· 84.5% built
- MAHAVIR ANANT8.5 yr overdueRAHUL PUKHRAJ SINGHVI · Ulawe, RaigarhP52000012352· 90.9% built
- SAI AARADHYA8.5 yr overdueM/S PILLARS INDIA CONSTRUCTIONS · Ulawe, RaigarhP52000010167· 58.5% built
- MARBLE ARCH8.5 yr overdueSHINING SUN CONSTRUCTIONS · Panvel, RaigarhP52000013234· 98.2% built· 1 complaint
- PRIME NEW HORIZON8.4 yr overduePRASHANT CHANDRAKANT BHOIR · Pen (M Cl), RaigarhP52000004080· 79.5% built
- SOHAM PRATHAMESH8.4 yr overdueSOHAM BUILDERS · Deulwadi, RaigarhP52000012015· 51.4% built
- SHREYAS VILLA8.4 yr overdueVINODRAI PREMJIBHAI TRAPASIA · Karanjade, RaigarhP52000010176· 90.9% built
- RAM SUBHADRA8.4 yr overdueRachana Construction · Panvel, RaigarhP52000010669· 90.9% built
- LAMER RESIDENCY8.4 yr overdueLAMER DEVELOPERS · Panvel, RaigarhP52000002060· 90% built
- NEEL GALAXY8.4 yr overdueNEELKANTHESHWAR CONSTRUCTION · Karanjade, RaigarhP52000007270· 79.2% built
- Esquire Homes - B8.4 yr overdueEsquire Realtors · Panvel, RaigarhP52000012887· 90.9% built
- SAURABH APARTMENT8.4 yr overdueTARACHAND HASTIMAL CHHAJED · Bopele, RaigarhP52000012557· 78.6% built
- SAMARTH RESIDENCY8.4 yr overdueSIDDHI DEVELOPERS · Ulawe, RaigarhP52000010559· filed Dec 2017 → now Mar 2018· 99.5% built
- Vasant Paradise8.4 yr overdueShri Vasant Developers · Karjat, RaigarhP52000011025· 80% built
- Samarth Samruddhi8.4 yr overdueMandar Madhukar Karandikar · Pen (M Cl), RaigarhP52000007981· 43.2% built
- Lamer Solitaire8.4 yr overdueLAMER DEVELOPERS · Panvel, RaigarhP52000004491· 89.1% built
- CLASSIC RESIDENCY8.4 yr overdueCLASSIC CONVENTURE · Uran, RaigarhP52000002944· 75.9% built
- BALAJI GARDEN8.4 yr overdueSHREE BALAJI ENTERPRISES · Malyan, RaigarhP52000009986· 90.9% built
- NIRAVANA ENCLAVE8.4 yr overdueJAGDISH LAKHMICHAND MOHINANI · Neral, RaigarhP52000001635· 90.9% built
- Esquire homes - A8.4 yr overdueEsquire Realtors · Panvel, RaigarhP52000012661· 90.9% built
- VANKVANIS ELA8.4 yr overdueSuresh Vankvani · Ulawe, RaigarhP52000007221· 49.5% built· 4 complaints
- GOVIND HARMONY8.4 yr overduePRIYAL HOMES · Panvel, RaigarhP52000002096· 82.7% built
- BALAJI COMPLEX - PLOT NO 11, 12, 138.4 yr overdueBALAJI INFRA · Khalapur, RaigarhP52000001600· 90.9% built
- POOJA ANGAN8.4 yr overdueRAJENDRA THORAT · KARANJADE, RaigarhP52000002558· 76.2% built
- ROYAL PRIDE8.4 yr overdueROYAL BUILDERS AND DEVELOPERS · Panvel, RaigarhP52000002329· 90.9% built
- Shivalic Heights8.4 yr overdueGeetanjali Construction · Panvel, RaigarhP52000004882· 90.9% built
- SAI ANCHIT8.4 yr overdueVANDANA PRASHANT PINGLE · Karanjade, RaigarhP52000009263· 66.7% built
- SAI SAMRUDDHI8.4 yr overdueOM SAI CONSTRUCTION · Nadgaon Tarf Birwadi (CT), RaigarhP52000011177· 37.3% built
- GENESIS8.4 yr overdueTODAY PRACHAR REALTY · Panvel, RaigarhP52000002114· 90.9% built
- SAVITRI NIWAS8.4 yr overdueRAMESH GULAB TUPE · Chinchpada, RaigarhP52000011962· 90.9% built
- SKYLINE CORNER8.4 yr overdueSKYLINE DEVELOPERS · Karanjade, RaigarhP52000007766· 90.9% built
- Ashiyana C.H.S Redevelopment8.4 yr overduePUNIT ENTERPRISES · Panvel, RaigarhP52000007021· 90.9% built
- HIRAYS ANGELICA8.4 yr overdueJAGANNATH DASHARATH HIRAY · Ulawe, RaigarhP52000002616· 90.9% built
- PRAMUKH PARADISE8.4 yr overduePRAMUKH DEVELOPERS · Panvel, RaigarhP52000004384· 90.9% built
- THE DREAM8.4 yr overdueTRIVENI BUILDERS& DEVELOPERS · Panvel, RaigarhP52000003799· 83.8% built· 1 complaint
- DEVKI PLAZA8.4 yr overduePOWER INFRA DEVELOPERS · Panvel, RaigarhP52000009782· 76.4% built
- EXCELLENCE RESIDENCY8.3 yr overdueEXCELLENCE INFRA · Panvel, RaigarhP52000005743· 69.1% built
- SHIV DRISHTI8.3 yr overdueSHIVKRUPA ENTERPRISES · Karanjade, RaigarhP52000003991· 77.7% built
- TULSI CORNER8.3 yr overdueMAHADEV LIFESPACES · Ulawe, RaigarhP52000003668· 80.9% built
- SHIV ASHIRWAD8.3 yr overdueSHIVKRUPA ENTERPRISES · Karanjade, RaigarhP52000010827· 72.5% built
- VANKVANIS BLISS8.3 yr overdueRahul Suresh Vankvani · Ulawe, RaigarhP52000011609· 3.6% built
- SEA STAR8.3 yr overdueRAJESH AND DSOUZA ASSOCIATES · Ulawe, RaigarhP52000011974· 86.8% built· 4 complaints
- SHASHWAT SANKUL8.3 yr overdueSAI SMARAN CONSTRUCTION · Bopele, RaigarhP52000007561· 68.6% built
- PARVATI AVENUE8.3 yr overdueR D Realtors · Panvel, RaigarhP52000005819· 90.9% built
- Pushpak8.3 yr overdueA R Constructions · Karanjade, RaigarhP52000001781· 90.9% built
- Rajesh Presidency8.3 yr overdueSAI SHRI HOME MAKERS · Ulawe, RaigarhP52000011010· 88.2% built· 3 complaints
- SABHARI CO-OP HSG SOCIETY8.3 yr overdueSHUBHAM ENTERPRISES · ULWE, RaigarhP52000010782· 90.9% built
- BHOSALE DAFFODIL8.2 yr overdueBHOSALE HOMES · Ulawe, RaigarhP52000005903· 75.5% built
- BLUE KEY REALTYS ESCALATE8.2 yr overdueBlue Key Realty · Ulawe, RaigarhP52000003043· 70.6% built
- PRAMUKH DARSHAN8.2 yr overduePRAMUKH ENTERPRISES · Dhamote, RaigarhP52000010357· 90.9% built
- SHREE MAHALAKSHMI PARK BUILDING NO 18.2 yr overdueSHREE MAHALAXMI HOME MAKERS · Dhamote,Neral, RaigarhP52000010984· 90.9% built
- NAKSHTRA PLAZA8.2 yr overdueSHARVARI BUILDERS & DEVELOPERS · Pen (M Cl), RaigarhP52000011253· 50% built
- BHUVANESHWAR PLAZA8.2 yr overdueOM BUILDERS · Bhuwaneshwar (CT), RaigarhP52000010401· 80% built
- BHOSALE TULIP8.2 yr overdueBHOSALE GROUP · Ulawe, RaigarhP52000012566· 78.2% built
- SAI SHRUSTI8.2 yr overdueSAI ENTERPRISES · Mahad (M Cl), RaigarhP52000008583· 60% built
- SHIVSHANKAR KALASH8.2 yr overdueSURESH SHIVSHANKAR SHARMA · Navi Mumbai Panvel Rigardh (CT), RaigarhP52000010959· 90.9% built
- SIDDHI ENTERPRISES8.1 yr overdueSIDDHI ENTERPRISES · Bopele, RaigarhP52000004194· 90.9% built
- SHREM SILVER BEACH8.1 yr overdueHitesh RamPraksash Chhatwal · Alibag, RaigarhP52000012541· filed Mar 2018 → now Jun 2018· 70.9% built
- Skyline riverside wing G8.1 yr overdueSkyline Millars Limited · Karjat, RaigarhP52000003852· filed Dec 2017 → now Jun 2018· 90.9% built
- Shubharambh Heritage8.1 yr overdueM/s Shubharambh Realty · Panvel, RaigarhP52000009499· 81.8% built
- CALLISTO8.1 yr overdueTODAY GLOBAL ENTERPRISES · Panvel, RaigarhP52000004871· 81.8% built
- Sonai Residency8.1 yr overdueAayushi Enterprises · Karanjade, RaigarhP52000006156· 72.7% built
- HARI ANMOL8.1 yr overdueHARI OM ENTERPRISE · Ulawe, RaigarhP52000012646· 41% built
- RAVECHI COMPLEX8.1 yr overdueLIVE ENTERPRISES · Karanjade, RaigarhP52000003850· 81.8% built
- SMART HEIGHTS8.1 yr overdueMUBIN MOHAMMED IQBAL JUMANI · Khopoli, RaigarhP52000012807· 66.4% built
- ANANT AURA8.1 yr overdueANANT INFRA · Panvel, RaigarhP52000003434· 90.9% built
- PACIFIC AURA8.1 yr overduePACIFIC ENTERPRISES · Panvel, RaigarhP52000004638· 90.9% built
- TATER FLORENCE OLIVE8.1 yr overdueTATER REALTY · Karjat, RaigarhP52000003313· 90.9% built
- TATER FLORENCE ORCHID8.1 yr overdueTATER REALTY · Karjat, RaigarhP52000003661· 90.9% built
- HARI OM DARSHAN8.1 yr overdueHARI OM ENTERPRISE · Ulawe, RaigarhP52000012855· 42.7% built
- Olympeo Riverside - Phase 18.1 yr overdueOlympeo Riverside Projects LLP · Neral, RaigarhP52000002351· 76.7% built
- PRAJAPATI VIHAR8.1 yr overduePRAJAPATI CONSTRUCTIONS LIMITED · Uran, RaigarhP52000002200· 90.9% built· 1 complaint
- PARVATI AANGAN8.1 yr overdueR D INFRA · Panvel, RaigarhP52000009728· 76% built
- SIDDHIVINAYAK TWINS8.1 yr overdueLACHHMAN VASDEV BATHIJA · Kalamboli, RaigarhP52000003619· 80.5% built· 6 complaints
- TITANIUM WOODS8.1 yr overdueTITANIUM CONSTRUCTION COMPANY · Panvel, RaigarhP52000001013· 90.1% built
- SAPHIRE ORIEL8.1 yr overdueSAPHIRE ASSOCIATES · Karanjade, RaigarhP52000003173· 89.1% built· 1 complaint
- Today royal elisium8.1 yr overdueTODAY ROYAL BUILDERS & DEVELOPERS · Karanjade, RaigarhP52000001258· 86.6% built
- SND SIGNATURE8.1 yr overdueS N DAMANI INFRA PRIVATE LIMITED · ULWE, RaigarhP52000008586· 90.9% built
- SHIVGANESH8.1 yr overdueVISHWANATH MADHUKAR MHATRE · Pargaon, RaigarhP52000013379· 65% built
- HARI OM NIRMAL8.1 yr overdueHARI OM ENTERPRISE · Ulawe, RaigarhP52000012709· 49.1% built· 5 complaints
- Jay Raj Deep Apartement8.1 yr overdueJay raj Deep Corporation · Dronagiri, RaigarhP52000014667· 72.5% built
- SAI DHAM8.1 yr overdueNAMDEV KASHINATH PATIL · Panvel, RaigarhP52000008443· 80% built
- Discover Condos8.1 yr overdueSilvex Realty Private Limited · Karjat, RaigarhP52000006498· 78.2% built
- PRABHAVATI COMPLEX8.1 yr overdueRAHIL ROSHAN SOMJEE · Pen (M Cl), RaigarhP52000012067· 55.5% built
- SIDDHIVINAYAK RESIDENCY8.1 yr overdueVIJAY AMRUTRAO SALVI · Ulawe, RaigarhP52000012280· 71.4% built
- ROSABELLA BUILDING NUMBER 28.1 yr overdueSVS GROUPS · Karjat, RaigarhP52000007466· 90.9% built
- BRAMHA RESIDENCY B8.1 yr overdueSHREE BRAMHA ENTERPRISES · Mamdapur, RaigarhP52000006789· 59.1% built
- VAKRATUNDA RESIDENCY8.1 yr overdueS CUBE BUILDCON · Kalundre (CT), RaigarhP52000013046· 36.8% built
- Zinnia8.1 yr overdueAdhiraj Constructions Private Limited · Panvel, RaigarhP52000009171· 72.7% built
- Omkar Apartments8.1 yr overdueDurvankur Developers · Panvel, RaigarhP52000012831· 80.9% built
- SHREE SARASWATI ARCADE8.1 yr overdueJITENDRA GOVARDHAN MHATRE · Panvel, RaigarhP52000011021· 90.9% built
- Mahindra The Serenes- 8 Villas8.0 yr overdueMahindra Lifespace Developers limited · Nagaon, RaigarhP52000000461· filed Jun 2018 → now Aug 2018· 78.2% built
- YASH HOMES8.0 yr overdueNILESH NAIK · Navade, RaigarhP52000010629· 75.9% built
- SHREE HINGAD PALACE8.0 yr overdueS.M. DEVELOPERS · Dhamote, RaigarhP52000008554· 73.6% built
- MISRI VILLA HEIGHT8.0 yr overdueSHREY INFRA PROJECT · Uran, RaigarhP52000003140· filed May 2018 → now Aug 2018· 72.8% built
- DEEP PRIDE8.0 yr overdueKIRTI SHAH · Karanjade, RaigarhP52000000770· 72.7% built
- VARDHMAN VATIKA8.0 yr overdueKashyap And Associates · Karanjade, RaigarhP52000003204· 62.7% built
- KRISHNA KUNJ8.0 yr overdueGLOBE HITECH BUILDERS · Panvel, RaigarhP52000003790· 61.4% built
- HILL VIEW8.0 yr overdueGAD REALTY · NERAL, RaigarhP52000015312· 64.3% built
- AMARPREET8.0 yr overdueAMARDEEP DEVELOPERS · Mamdapur, RaigarhP52000008784· 85.7% built
- DEEP RISE8.0 yr overdueKIRTI SHAH · Panvel, RaigarhP52000000516· 72.7% built
- VAISHNAVI8.0 yr overduePRAMOD VASANT BHOIR · Uran, RaigarhP52000008787· 85.5% built
- GOVIND CHHAYA7.9 yr overdueEURO REALITY · Navade, RaigarhP52000012790· 76.4% built
- TULSI AASHRAY7.9 yr overdueSHUBH ENTERPRISES · Pashane, RaigarhP52000000020· 90.9% built
- SHREE GANESH7.9 yr overdueNAVEEN OMPRAKASH JAISWAL · Panvel, RaigarhP52000009973· 90.9% built
- HIMALAYA COMPLEX7.9 yr overdueHIMALAYA BUILDERS AND DEVELOPERS LLP · Pashane, RaigarhP99000004617· 84.1% built
- SHIV SADAN7.9 yr overdueSANIYA DEVELOPERS · Pen (M Cl), RaigarhP52000010956· 38.2% built
- DURGA RESIDENCY7.9 yr overdueSHREE GANESH BUILDERS & DEVELOPERS · Panvel, RaigarhP52000011005· 50% built
- SAIRAJ GOLDEN VIEW7.9 yr overdueSHIVAM DEVELOPER · Panvel, RaigarhP52000006625· filed Dec 2017 → now Sept 2018· 56.9% built
- LANDMARK7.9 yr overdueLANDINFRA DEVELOPERS · Karanjade, RaigarhP52000001621· 56.4% built
- MEERA ENCLAVE7.9 yr overdueSUNRAYS CONSTRUCTIONS · Panvel, RaigarhP52000010678· 47.3% built
- APEX NEST7.9 yr overdueAPEX GROUP · Karanjade, RaigarhP52000005821· 90.9% built
- PRIDE VILLA7.8 yr overduePride Builders · Ulawe, RaigarhP52000003405· 90.9% built
- Sai Radiance7.8 yr overduePRASAD ESTATE · Panvel, RaigarhP52000006076· 36.9% built
- GOURI VARADVINAYAK7.8 yr overdueSHANKAR SADU MHATRE · Khopoli, RaigarhP52000011255· 41.3% built
- SHIVAMRIT COMPLEX7.8 yr overdueBHARATI DHARMA JOSHI · Ulawe, RaigarhP52000005184· 65.1% built
- Landmaark Lexus7.8 yr overdueSagar Ravindra Malwade · Ulawe, RaigarhP52000007361· 90.9% built
- JAI NEELKANTH7.8 yr overdueM/S JAI DEVELOPERS · Panvel, RaigarhP52000007385· 54.5% built
- KESHAV WINDS7.8 yr overdueWINDFIELD STOCKS AND SECURITIES PVT LTD · Panvel, RaigarhP52000008209· filed Apr 2018 → now Oct 2018· 95.9% built
- AB EXOTICA7.8 yr overdueAB BUDGET HOMES · Uran, RaigarhP52000009570· 49.1% built
- VARD VINAYAK7.8 yr overdueSHREE VARDVINAYAK ENTERPRISES · Karanjade, RaigarhP52000003001· 68.2% built
- MORAJ MAA SHRISHTI7.7 yr overdueMORAJ INFRATECH PRIVATE LIMITED · Khalapur, RaigarhP52000000480· 32.7% built
- AARTI PRIDE7.7 yr overdueRAMESH BANDU RETAREKAR · UPPER KHOPOLI, RaigarhP52000015340· 58.2% built
- DHARTI VILLA7.7 yr overdueRHYTHM ENTERPRISES · Ulawe, RaigarhP52000001102· 66.5% built
- OM IMPERIA7.7 yr overdueCAPITAL ASSOCIATES · Karanjade, RaigarhP52000003265· 75% built· 1 complaint
- ROYAL PLAZA7.6 yr overdueRoyal Enterprise · Khopoli, RaigarhP52000011853· 68.9% built
- Muneera Heights7.6 yr overdueIsmail Hamdule · Kamothe, RaigarhP52000009492· 90.9% built
- ARIHANT ANAIKA PHASE I7.6 yr overdueARIHANT VATIKA REALTY PRIVATE LIMITED · Panvel, RaigarhP52000001869· 89.1% built· 1 complaint
- ARIHANT AMISHA PHASE I7.6 yr overdueARIHANT AASHIYANA PRIVATE LIMITED · Panvel, RaigarhP52000008203· 89.1% built
- SUKHKARTA 17.6 yr overdueIMAGE BUILDERS · Khopoli, RaigarhP52000010590· 47.7% built
- AAIJI HILLS7.6 yr overdueOM SAI DEVELOPERS · KARANJADE, RaigarhP52000010921· 65.6% built
- PANCHRATNA PARK7.6 yr overdueHINDUSTAN CONSTRUCTION BUILDERS & DEVELOPERS · Panvel, RaigarhP52000008794· 81.3% built
- Blue Crest7.6 yr overdueElinor Infra LLP · Karanjade, RaigarhP52000009702· 80.3% built· 1 complaint
- PRIME7.6 yr overdueESS GEE TRADEFIN PVT LTD · Uran, RaigarhP52000003474· 90.9% built
- GURU AANGAN7.6 yr overdueFSK BUILDERS & DEVELOPERS PRIVATE LIMITED · Ulawe, RaigarhP52000010422· 35.5% built
- SIDDHIVINAYAK GARIMA7.6 yr overdueSIDDHIVINAYAK HOMES · Panvel, RaigarhP52000001125· 89.1% built
- SHREE HARI NISARG RESIDENCY7.6 yr overdueSHREE HARI REALTORS · Bopele, RaigarhP52000001148· 90.9% built
- PRAGATI AVENUE7.6 yr overduePRAGATI REALTY · -, RaigarhP52000012345· 68.1% built
- DHRUV RESIDENCY PHASE EXCELLENCY KWING7.6 yr overdueDHRUV ASSOCIATES · Pashane, RaigarhP52000007640· 81.8% built
- TARIQUE SAPPHIRE7.6 yr overdueKOHINOOR DEVELOOPERS AND REALTORS · Panvel, RaigarhP52000010945· 61.8% built
- SATYAM APARTMENT7.6 yr overdueSHANTI DEVELOPERS · Taloje Panchnad, RaigarhP52000012326· 45% built
- BHOSALE MARIGOLD7.6 yr overdueLEENA ARJUN GARAD · Ulawe, RaigarhP52000012668· 90.9% built
- REDWOOD ICON7.6 yr overdueREDWOOD BUILDCON · Pen (M Cl), RaigarhP52000009374· 54.5% built
- SIDDHIVINAYAK HERITAGE7.6 yr overdueSIDDHIVINAYAK DEVELOPERS · Panvel, RaigarhP52000002557· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.