High risk
  • Possession date passed. The proposed possession date (Apr 2018) has passed with construction at 69.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2018 per the RERA filing.
Satellite view of this address

Where it is · 53, Panvel

Promoter

Builder profile

Builder
EXCELLENCE INFRA

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000005743
Status
Ongoing
Stage
Certificate Signed
Possession
April 2018
Construction
69.1% complete
Units sold
0 of 0