Delayed projects in Nashik
985 MahaRERA-registered projects in Nashik are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 1 of 5
- Dhatrak Heights8.6 yr overdueKhilendrakumar Dilip Mohabiya · Nashik (M Corp.), NashikP51600005757· 90.6% built
- SAMARTH HEIGHT8.6 yr overdueJAYASHREE DEVELOPERS · Nashik (M Corp.), NashikP51600013758· 90.9% built
- Le Regalia Phase I BLDG C AND D8.6 yr overdueM/s. ShreePrakash Creative Buildcon J.V. · Nashik (M Corp.), NashikP51600009453· 90.9% built
- GANADHISH8.6 yr overdueGANESH ENTERPRISES · anandvalli, NashikP51600004373· 90.9% built
- Aashrayan Apartment8.6 yr overdueSwapnavel Builders & Developers · Nashik, NashikP51600013037· 90.9% built
- Anand Sagar8.6 yr overdueSagar Constructions · Nashik (M Corp.), NashikP51600011939· 90% built
- KULASHREE NEST8.6 yr overdueKULSHREE DEVELOPERS · Nashik (M Corp.), NashikP51600013530· 73.6% built
- GREEN ACRE8.6 yr overdueFARAZ ASLAM MULLA · Deolali (CB), NashikP51600005270· 89.1% built
- Gurukripa Appartment8.6 yr overdueROYAL DEVELOPERS · Nashik (M Corp.), NashikP51600011997· 81.8% built
- Soham8.6 yr overdueS B Constructions · Nashik (M Corp.), NashikP51600013041· 81.8% built
- SAMARTH ANNEX8.6 yr overdueOM SAI BUILDCON · Nashik (M Corp.), NashikP51600006646· 81.8% built
- SHREE SAI PLAZA8.6 yr overdueSHREE SAI BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600005859· 81.8% built
- ATHASHREE8.6 yr overdueSAPALE AGASHE ASSOCIATES · Nashik, NashikP51600005309· 81.8% built
- SHREE TULSI KUNJ8.6 yr overdueSHREE ENTERPRISES · DINDORI ROAD, NashikP51600012894· 90.9% built
- Business Park8.6 yr overdueRoongta Buildcon Ltd. · Nashik, NashikP51600006641· 60.7% built
- AMRUT SHILP8.6 yr overdueSUPRABHAT CONSTRUCTIONS · Nashik, NashikP51600012316· 90.9% built
- ARYA APPARTMENT8.6 yr overduePURUSHOTTAM MOHAN RAMPARIYA · Nashik (M Corp.), NashikP51600002981· 67.5% built
- Sadguru Apartment8.6 yr overdueV R Construction · Nashik (M Corp.), NashikP51600008773· 90.9% built
- KARMAA GALAXY8.6 yr overdueKARMAA REALTY · Nashik (M Corp.), NashikP51600003024· 60% built
- MALPANI SAFFRON BUILDING NO 28.6 yr overdueGIRIRAJ ENTERPRISES · Nashik (M Corp.), NashikP51600008125· 72.7% built· 3 complaints
- SHREE GANESHA PARK8.6 yr overdueKRANTI BUILDCON · Nashik, NashikP51600013040· 72.7% built
- SATYAM PALACE8.6 yr overdueGEETA BUILDCON · BEHIND NIGAL PARK, NashikP51600012514· 81.8% built
- PRATHMESH PARK8.6 yr overdueSAKAR GROUP · Nashik, NashikP51600012881· 90.9% built
- Crown Residency8.6 yr overdueCROWN MAKERS BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600011764· 90.9% built
- GURUKRUPA HEIGHTS8.6 yr overdueSANJAY KASHINATH SAYANKAR · Indiranagar, NashikP51600010234· 81.8% built
- OMKAR APARTMENT8.6 yr overdueVIMALBHAI PARBATBHAI TOGADIYA · Nashik, NashikP51600003946· 90.9% built
- HARI ANAND8.6 yr overdueDHARAN INFRA-EPC LIMITED · Nashik, NashikP51600001348· 90.9% built
- Bhoomi Vijay Apartment8.6 yr overdueNarayan Jankiram Deshpande · Nashik, NashikP51600012879· 74.5% built
- RUTUGANDH8.6 yr overdueROOPAYAN LIFSTYLE · Nashik, NashikP51600006166· 90.9% built
- New Shiv Shubham8.6 yr overdueWaghandCompany · Nashik Road, NashikP51600013437· 90.9% built
- GOKULDHAM APPARTMENT8.6 yr overdueSHREE BALAJI BUILDERS AND DEVELOPERS · NASHIK, NashikP51600009696· 90.9% built
- SUNNY DEVELOPERS8.6 yr overdueSUNNY DEVELOPERS · Nashik, NashikP51600008674· 96.4% built
- SUKHSAGAR NX8.6 yr overdueSagar Constructions · Nashik (M Corp.), NashikP51600012739· 81.8% built
- Bajrang8.6 yr overdueNarsibhai Mavjibhai Mavani · Nashik (M Corp.), NashikP51600011049· 90.9% built
- MAHADEV CORNER8.6 yr overdueMAHADEV CONSTRUCTION · Nashik, NashikP51600008031· 90% built
- OMKAR DEEP8.5 yr overdueOMKAR BUIDCON · Nashik (M Corp.), NashikP51600007514· 90.9% built
- SHRI SHRI SAGAR8.5 yr overdueSagar Constructions · Nashik (M Corp.), NashikP51600012595· 81.8% built
- ROYAL ORCHID8.5 yr overdueBALAJI BUILDCON · Upnagar, NashikP51600006397· 70.5% built
- SAMRUDDHI PRIDE8.4 yr overdueSAMRUDDHI BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600006644· 81.8% built
- Sukruti Elite8.4 yr overdueSukruti Constructions · Nashik (M Corp.), NashikP51600010612· 90.9% built
- AROHI APARTMENT8.4 yr overdueNEW AKSHARA CONSTRUCTION · Nashik (M Corp.), NashikP51600008837· 90.9% built
- AANUSHREE RESIDENCY8.4 yr overdueABHAY CHANDMAL JAIN · Indiranagar, NashikP51600000075· 30.3% built
- HARI SPARSH II8.4 yr overdueDHARAN INFRA-EPC LIMITED · Bhagur Rural, NashikP51600000119· 69.1% built
- VRINDAVAN HEIGHT8.4 yr overdueSHIVSAI BUILDCON · Nashik, NashikP51600008519· 90.9% built
- SHREE SIDDHI RESIDENCY8.4 yr overdueSIDDHIVINAYAK DEVELOPERS · PIMPALGAON BAHULA SHIVAR, SRAMIKNGAR, NashikP51600012965· 90.9% built
- YAMUNA ROW BUNGLOW8.4 yr overdueSHRI SAI CONSTRUCTION · Nashik, NashikP51600012798· 81.8% built
- SUKH SAGAR8.4 yr overdueSagar Constructions · Nashik (M Corp.), NashikP51600012549· 63.8% built
- Navshya Elite8.4 yr overdueDhruv Developers · Aanandwali, NashikP51600009682· filed Dec 2017 → now Mar 2018· 81.8% built
- SAMARTH EMPIRE8.4 yr overdueSAGAR PRAKASH BURHADE · Nashik, NashikP51600012439· 81.8% built
- WHITE FIELDS8.4 yr overduePAVAN SANJIV TUPSAKHARE · Nashik, NashikP51600011670· 90.9% built
- ISHWAR PRESTIGE8.4 yr overdueSHANKAR GHANSHYAMDAS SAMNANI · Aanandwali, NashikP51600012272· 72.7% built
- United Sanskruti Phase I8.4 yr overdueUnited Builders · Nashik, NashikP51600001099· 86.1% built
- AASTHA RESIDENCY8.4 yr overdueYASH BUILDCON · Nashik (M Corp.), NashikP51600010855· 90.9% built
- PRABHU SPARSH8.4 yr overduePACIFIC HOUSING CORPORATION · Nashik, NashikP51600006443· 90.9% built
- Anushree Apartment8.4 yr overdueRavi Mahajan ( HUF ) · Nashik, NashikP51600003905· 90.9% built
- KUNAL RESIDENCY8.4 yr overdueKUNAL BUILDERS AND DEVELOPERS · Mhasrul, NashikP51600003606· 90.9% built
- NIRMITI LIFESPACE8.4 yr overdueNIRMITI LIFESTYLE · Nashik, NashikP51600008064· 81.8% built
- Suniket Business Center8.4 yr overdueSuniketBuildersandDevelopers · Nashik (M Corp.), NashikP51600012237· 81.8% built
- SHRAVANAM RESIDENCY8.4 yr overduePRADEEP NARAYAN PAWAR HUF · Aanandwali, NashikP51600009252· 90.9% built
- YAMUNA NIWAS AND PARK ROW BUNGLOW8.4 yr overdueSHRI SAI CONSTRUCTION · Nashik, NashikP51600013332· 81.8% built
- UTKARSHA HIGHTS8.4 yr overdueNEW AKSHARA CONSTRUCTION · Nashik (M Corp.), NashikP51600009858· 90.9% built
- GAJANAN KRUPA8.3 yr overdueGAJANAN DEVELOPERS · Nashik, NashikP51600005519· 90.5% built
- HARIDEEP SQUARE8.2 yr overdueHARIDEEP DEVELOPERS · Nashik (M Corp.), NashikP51600010848· 90.9% built
- SAI NIRMAL APPARTMENT8.2 yr overdueSAMRUDDHI CONSTRUCTION · Nashik, NashikP51600004394· 47.7% built
- LIBERTY NIWAS8.2 yr overdueSHRISHTI BUILDCON · Nashik, NashikP51600003961· 90.9% built
- SHIVDHARA8.2 yr overdueGEETA BUILDCON · Adgaon, NashikP51600010746· 78.2% built
- The Metrozone Aspen C28.1 yr overdueSanklecha Construction Private Limited · Nashik (M Corp.), NashikP51600009327· 90.9% built· 1 complaint
- AARADHYA RESIDENCY8.1 yr overdueABHAY CHANDMAL JAIN · Deolaligaon, NashikP51600000297· 36.4% built
- ROYALE B C D8.1 yr overdueAshoka Infraways Limited · Wadala, NashikP51600011935· filed Dec 2017 → now Jun 2018· 90.9% built
- USSH KIRAN8.1 yr overdueMangesh Dashrath Gaikar · Nashik (M Corp.), NashikP51600012292· 90.9% built
- LEELADHAR APARTMENT8.1 yr overdueSHREE KRISHNA BUILDERS · Nashik, NashikP51600006650· 51.8% built
- Parksyde Homes Phase 18.1 yr overdueJaikumar Constructions LLP · Nashik, NashikP51600002640· 97.7% built
- SHIV DARSHAN8.1 yr overdueVIJAY MAGANBHAI TANK · Nashik, NashikP51600012900· filed Dec 2017 → now Jun 2018· 52.3% built
- VANRAJ SUNSHINE8.1 yr overdueABHIJIT VAMANRAO PATIL · Nashik, NashikP51600009694· 81.8% built
- GAJANAN8.1 yr overdueSIDDHARTH RAMESH SHAH · Nashik (M Corp.), NashikP51600006982· 75.9% built
- SHREE GANESH APARTMENT8.1 yr overdueSUBHADRA PROPERTIES PRIVATE LIMITED · Nashik (M Corp.), NashikP51600007091· 83.6% built
- YASH ORCHID8.1 yr overdueYASH CONSTRUCTIONS · Nashik (M Corp.), NashikP51600010893· 39% built
- HARI VATIKA8.1 yr overdueDHARAN INFRA-EPC LIMITED · SANSARI, NashikP51600000220· 74.5% built
- ROONGTA TOWNSHIP PHASE IV APARTMENT8.1 yr overdueROONGTA BUILDERS AND DEVELOPERS · NASHIK, NashikP51600001287· 90.9% built
- BLUE HAVEN8.1 yr overdueTALWARE BUILDERS PRIVATE LIMITED · Aanandwali, NashikP51600014066· 73.6% built
- SPRINGFIELD8.1 yr overdueVASUNDHARA CONSTRUCTION · Nashik, NashikP51600011544· 51.8% built· 2 complaints
- Shree Krishna Residency8.1 yr overdueHemant Enterprises · Nashik, NashikP51600008003· 90.9% built
- Radha Krishna8.1 yr overdueBharat Lalji Mawani · Nashik, NashikP51600005317· 72.7% built
- BHAGYA HARI ROW BUNGLOW8.1 yr overdueBHAGYA DEVELOPER · Nashik, NashikP51600005560· 63.6% built
- BHASKAR AVENUE8.1 yr overdueTUKARAM TANAJI WAGH · Nashik (M Corp.), NashikP51600012842· 90.9% built
- SAMARTH PLAZA8.1 yr overdueTUKARAM TANAJI WAGH · Nashik, NashikP51600012058· 90.9% built
- KALPRAJ APARTMENT8.1 yr overdueAKAR DEVELOPERS · Deolaligaon, NashikP51600008297· 90.9% built
- GANANAYAK RESIDENCY8.1 yr overdueSANJAY MANSING SALUNKHE · Nashik (M Corp.), NashikP51600004992· 81.8% built
- SHREE HARI APARTMENT8.1 yr overdueKISHOR JIVRAJBHAI JETHVA · Nashik, NashikP51600006111· 80.9% built
- DURGA APARTMENT8.1 yr overduePRABHUDAS LAXMAN PATEL · Jail Road, NashikP51600008548· 90.9% built
- LOTUS PARK APARTMENT8.1 yr overdueLOTUS REALTY · Nashik (M Corp.), NashikP51600004238· 90.9% built
- SAHAJANAND HEIGHTS8.1 yr overdueSHYAM CORPORATION · PANCHAVATI, NashikP51600005263· 90.9% built
- Klassic Heights8.1 yr overdueVimla Jashanmal Jagger · Nashik, NashikP51600007189· 90.9% built
- SHREERAM CASTLE8.1 yr overdueSHREERAM BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600006998· 90.9% built
- VAKRATUNDA APPARTMENT8.1 yr overdueICCHAMANI DEVELOPERS · Nashik, NashikP51600006394· 55.9% built
- SWAMINARAYANPARK8.1 yr overduePRAMOD VASUDEO ZAMBRE · Nashik (M Corp.), NashikP51600012604· 71.8% built
- DAMODAR HEIGHTS8.1 yr overdueSUBHAM BABULAL DHOLU · RANE NAGAR, NashikP51600011058· 68.2% built
- Prestige Residency8.1 yr overdueK For Kathiyawad Developers · Nashik, NashikP51600006827· 68.2% built
- Husaini Tower8.0 yr overdueCITIZEN CONSTRUWELL · Nashik, NashikP51600010969· 90.9% built
- SHREE TIRUMALA VASANT APARTMENT8.0 yr overdueSHREE TIRUMALA DEVELOPERS · Nashik, NashikP51600001697· 81.8% built
- SHREE YOG ROW BUNGLOW8.0 yr overdueSHIVAM REALTORS · Nashik, NashikP51600008328· 90.9% built
- SAI PRERNA APARTMENT8.0 yr overdueJATINBHAI GOPALBHAI GOL · Nashik (M Corp.), NashikP51600011931· 90.9% built
- SHIVALIK RESIDENCY8.0 yr overdueBHARAT VITHALBHAI AJUGIA · Nashik Road, NashikP51600007978· 51.5% built
- SHRIPAD RESIDENCY8.0 yr overdueVAASTU VAIBHAV CONSTRUCTIONS · Panchak, NashikP51600008644· 90.9% built
- PARIJAT SAHNIWAS8.0 yr overdueANIKET ANANT PATIL · Nashik (M Corp.), NashikP51600005366· 90.9% built
- Royal Empire8.0 yr overduePekhale Patil Construction · Nashik (M Corp.), NashikP51600005059· 90.9% built
- Thakkers Paradise8.0 yr overdueMotel Kutir Nirman Pvt. Ltd. · Nashik, NashikP51600003938· 70.5% built
- SIDDHIVINAYAK RESIDENCY8.0 yr overdueM/S. SIDDHI VINAYAK CONSTRUCTION · NASHIK MUNICIPAL CORPORATION, NashikP51600015942· 72.7% built
- Thakkers Richmond Heights8.0 yr overduePratap Marketing Pvt Ltd · Nashik, NashikP51600008267· 81.8% built
- Arsh Residency8.0 yr overdueTabeer Properties · Rehnuma Nagar, NashikP51600005289· 90.9% built
- SHREE SAI RESIDENCY8.0 yr overdueSHREE SAI CONSTRUCTIONS · Nashik (M Corp.), NashikP51600009143· 58.6% built
- HARI NAMAN7.9 yr overdueDHARAN INFRA-EPC LIMITED · Deolaligaon, NashikP51600000228· filed Dec 2017 → now Sept 2018· 81.8% built
- SPACE ORION BUILDING E7.9 yr overdueSPACE DEVELOPERS CORPORATION JOINT VENTURE · Dada Saheb Phalke Road, NashikP51600005108· 90.9% built
- AARYAVARTA SECTOR 4 - B TO H7.9 yr overdueLINKER SHELTER PRIVATE LIMITED · Nashik, NashikP51600002169· filed May 2018 → now Sept 2018· 90.9% built· 12 complaints
- The Metrozone Athens A17.9 yr overdueSanklecha Construction Private Limited · INDIRA NAGAR, NashikP51600005033· filed Mar 2018 → now Sept 2018· 90.9% built· 5 complaints
- The Metrozone Aspen C17.9 yr overdueSanklecha Construction Private Limited · INDIRA NAGAR, NashikP51600005208· filed Mar 2018 → now Sept 2018· 90.9% built· 1 complaint
- GURU ASHISH APARTMENT A WING7.9 yr overdueVELANI DEVELOPERS · CHEHADI PUMPING ROAD, NashikP51600011898· 66.4% built
- The Metrozone Hampston B17.9 yr overdueSanklecha Construction Private Limited · INDIRA NAGAR, NashikP51600007133· filed Mar 2018 → now Sept 2018· 90.9% built
- SHREE RIDDHI SIDDHI DEVELOPERS7.8 yr overdueSHREE RIDDHI SIDDHI DEVELOPERS · Nashik (M Corp.), NashikP51600008972· 63.8% built
- ADIGURU7.8 yr overdueMAHAJAN BUILDCON · Nashik, NashikP51600003687· 90.9% built
- KSHITIJ CO OP HOUSING SOCIETY LIMITED7.8 yr overdueYOG BUILDERS AND DEVELOPERS · Nashik, NashikP51600012914· 73.2% built
- Raman Park - Phase - I7.8 yr overdueARHAM CONSTROTECH PVT LTD · Yeola, NashikP51600004598· 56.4% built
- Raj Laxmi7.8 yr overdueJANOEYA CONSTRUCTION · Nashik, NashikP51600011657· 90.9% built
- SAI HEIGHTS7.7 yr overdueKRISHNADEEP BUILDERS & DEVELOPERS · Nashik, NashikP51600011048· 89.1% built
- Shri Samarth Sai Niwas7.7 yr overdueShri Sai Samartha Constructions · SANSARI, NashikP51600009839· 84.8% built
- DARPAN TOWER APARTMENT7.7 yr overdueDILIP KARBHARI BHAMARE · PANCHAVATI, NashikP51600002845· 90.9% built
- subodh hights7.7 yr overdueS M BUILDERS AND DEVOLOPERS · Bhagur Rural, NashikP51600010874· 43.2% built
- GLENDALE COPERATIVE HOUSING SOCIETY LIMITED7.7 yr overdueGLENDALE COOPERATIVE HOUSING SOCIETY LIMITED · Nashik (M Corp.), NashikP51600007451· 76.4% built
- SHREE SAI ENCLAVE7.7 yr overdueSHREE SAI ASSOCIATES · Nashik (M Corp.), NashikP51600009958· 58.2% built
- MERU BHOOMI7.7 yr overdueAMIT BUILDERS · Deolali (CB), NashikP51600006374· 43.7% built
- Lotus Pride7.7 yr overdueLotus Buildcon · Pandav Nagri, NashikP51600007403· filed Dec 2017 → now Dec 2018· 90.9% built
- KALA RESIDENCY7.6 yr overdueVIJAY BHASKAR AHIRRAO · Nashik, NashikP51600007667· 90% built
- MOTKARIS GRAVITY7.6 yr overdueMOTKARI CONSTRUCTIONS PRIVATE LIMITED · Govind Nagar, NashikP51600007839· 90.9% built
- SURYA PARK-G7.6 yr overdueRAMCHANDRA VITTHAL SURYAWANSHI · PAWAR MALA OPP. RTO OFFICE, NashikP51600012959· 72.2% built
- Royal Palm7.6 yr overdueTabeer Properties · Khode Nagar, NashikP51600010474· 90.9% built
- Anmol Nayantara City One Phase 37.6 yr overdueBafna Realtors Pvt Ltd · Nashik, NashikP51600000354· 69.8% built
- VRINDAVAN7.6 yr overdueNIRMITI BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600004972· filed Dec 2017 → now Dec 2018· 89.5% built· 1 complaint
- Tirupati Garden Phase III7.6 yr overdueRIDDHI SIDDHI CONSTRUCTIONS · Bhagur (M Cl), NashikP51600008472· 90.9% built
- GANGADHAR NAGAR A WING7.6 yr overdueONKAR NIVRUTTI MAHALE HUF · Nashik, NashikP51600013925· 55.5% built
- VIJAY SONNET7.6 yr overdueJAY DEVELOPERS · Nashik (M Corp.), NashikP51600011372· 90.9% built
- TULIP TOWER7.6 yr overdueCLASSIC BUILDERS AND DEVELOPERS · NASHIK, NashikP51600015100· 85% built
- RENUKA PRASANNA7.6 yr overdueRENUKA DEVLOPERS · VIHITGAON, NashikP51600006623· 70.9% built
- RIDGEWOOD7.6 yr overdueTIRUPATI DEVELOPERS · OFF GANGAPUR ROAD, NashikP51600012301· 90.9% built
- NANDANVAN GARDEN APARTMENT7.6 yr overdueSHREE ASSOCIATES · Nashik (M Corp.), NashikP51600011042· 81.8% built
- Mirage7.6 yr overdueGREENWOOD BUILDER PVT LTD · Aanandwali, NashikP51600008731· 90.9% built
- Gokul 17.6 yr overdueGokul Infrastructure · Satpur, NashikP51600007108· 71.5% built
- SHREE VILLA7.6 yr overdueSHREE BUILD CRAFTS · Nashik (M Corp.), NashikP51600009776· 47.7% built
- TOWN SQUARRE7.6 yr overdueNIRMITI BUILDTECH · Panchavati, NashikP51600012818· 63.6% built
- Sejal Harmony7.6 yr overdueR R CONSTRUCTIONS · Nashik (M Corp.), NashikP51600012494· 81.8% built
- Anmol Nayantara City One Phase 17.6 yr overdueBafna Realtors Pvt Ltd · Nashik, NashikP51600000539· 79.6% built· 1 complaint
- VIJAYPARADISEPARK7.6 yr overdueJAY DEVELOPERS · Nashik (M Corp.), NashikP51600004967· 63.6% built
- ORBIT CASA7.6 yr overdueB-ORBIT VENTURES · Nashik, NashikP51600009915· 59.1% built
- EMPIREO HEIGHTS7.6 yr overduePINGALE BROTHERS · Nashik (M Corp.), NashikP51600007360· filed Dec 2017 → now Dec 2018· 90.9% built
- KAABIL APARTMENT7.6 yr overduePARVIN GAMIR SHAIKH · MAUJE WADALA SHIVAR, NashikP51600014779· 90.9% built
- Sai Aanand Plaza7.6 yr overdueVishwas Builders & Developers · Nashik (M Corp.), NashikP51600008613· 80.5% built
- SAMRUDHIPALACE7.6 yr overdueJAY DEVELOPERS · Nashik (M Corp.), NashikP51600010696· 90.9% built
- VIJAY GALAXY7.6 yr overdueJAYDEVELOPERS · Nashik (M Corp.), NashikP51600006062· 72.7% built
- Shree Gajanan Park7.6 yr overdueShree Buildcon & Associates · Deolaligaon, NashikP51600006279· 49.9% built
- VIJAY RESIDENCY7.6 yr overdueJAY DEVELOPERS · Aanandwali, NashikP51600007898· 72.7% built
- NANDAN SHILP7.6 yr overdueNARESHKUMAR JAYANTIBHAI PATEL · PRABHAT NAGAR, NashikP51600009425· 81.8% built
- RADHIKA PRIDE7.6 yr overdueBRIJWASI BUILDCON · Nashik (M Corp.), NashikP51600010716· 90.9% built
- Vastu shilp7.6 yr overdueShilp Buildcon · Nashik (M Corp.), NashikP51600007256· 45.5% built· 1 complaint
- M AND M COUNTY7.6 yr overdueM & M Infrasolutions Pvt. Ltd. · Nashik (M Corp.), NashikP51600011825· 83.2% built
- TIRUMALLA GLORY7.6 yr overdueSHREE VENKATESH DEVELOPERS · Nashik (M Corp.), NashikP51600011071· 90.5% built
- MORAYA APARTMENT7.6 yr overdueSIDDHARTH RAMESH SHAH · Makhmalabad, NashikP51600006906· 81.8% built
- KOTHARI CHAMBERS7.6 yr overdueNITIN DAYALAL KOTHARI · Nashik, NashikP51600006974· 89.1% built
- OM RESIDENCY APPARTMENT7.6 yr overdueSIDDHIVINAYAK BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600012992· 90.9% built
- SHREE SHYAM7.6 yr overdueKALPESH CHHAGANBHAI AJAGIYA · Panchvati, NashikP51600007475· 90.9% built
- VASUDEV APARTMENT7.6 yr overdueJAY BALAJI BUILDCON · Nashik (M Corp.), NashikP51600010213· 86.8% built
- NILANJAN SHRI7.6 yr overdueBY BUILDERS & DEVELOPERS · DRUVA NAGAR, NashikP51600005856· 90.9% built
- OJAS DREAM HOME7.6 yr overdueOJAS BUILD TECH · Nashik, NashikP51600010730· 36.4% built
- HARI KIRAN7.6 yr overdueKARDA BUILDCON PRIVATE LIMITED · VIHITGAON, NashikP51600000349· 90.9% built
- Anmol Nayantara City One phase 27.6 yr overdueBafna Realtors Pvt Ltd · Nashik, NashikP51600000565· 70.2% built· 1 complaint
- TREASURE PARK PHRASE -17.6 yr overdueKANAKLAXMI DEVELOPERS · Nashik, NashikP51600006300· filed Dec 2017 → now Dec 2018· 72.7% built
- Gurudev Heights7.6 yr overdueAmit Gangadhar Jadhav · Indiranagar, NashikP51600003352· 90.9% built
- KOMAL ORCHID7.6 yr overdueKISHAN HOLARAM ADWANI · WADALA, NashikP51600008588· 90.9% built
- SHREESAMARTH APARTMENT7.6 yr overdueSHREEYOG PROPERTIES · WADALA SHIWAR, NashikP51600000748· 90.9% built
- SHRI GIRIDHAR APARTMENT7.6 yr overdueLALIT BHANUBHAI KAMANI · Nashik, NashikP51600009585· 51.8% built
- SHAHS GOVIND APARTMENT PHASE I7.6 yr overdueSHAH BUILDERS AND DEVELOPERS · NEAR RENUKA MATA MANDIR, NashikP51600007197· 72.7% built
- SHREE SIDDHI VINAYAK APPARTMENT7.6 yr overdueRIDDHI SIDDI DEVELOPERS · Nashik (M Corp.), NashikP51600004980· 90.9% built
- SHILP KALA7.6 yr overdueSHILP KALA CO-OPERATIVE HOUSING SOCIETY LIMITED · Adarsh Nagar, NashikP51600009737· 81.8% built
- THE RENAISSANCE7.6 yr overdueVAKRATUNDA PROPERTIES · GOVIND NAGAR, NashikP51600006900· 90.9% built
- URJA RESIDENCY7.6 yr overdueURJA BUILDERS AND DEVELOPERS · KHODE MALA, NashikP51600014599· 71.8% built
- OM HEIGHTS7.6 yr overdueVISION ASSOCIATES · Nashik (M Corp.), NashikP51600011955· 90.9% built
- SHREE TIRUMALA SWASTIK APARTMENT7.6 yr overdueROONGTA HOMES LLP · Indiranagar, NashikP51600005646· 90.9% built
- KALYAN SAMRUDDHI7.6 yr overdueKALYAN TOLL INFRASTRUCTURE LTD · DHRUVA NAGAR, NashikP51600011079· 90.9% built
- VIJAY ROYAL7.6 yr overdueJAY DEVELOPERS · Nashik (M Corp.), NashikP51600011816· 81.8% built
- Gajanan Plaza Apartment7.6 yr overdueMahesh Joshi & Narendra Kulkarni Associates · Indira Nagar, NashikP51600004168· 90.9% built
- LOTUS COURT7.6 yr overdueBORA HOSPITALITY LLP · panchwati, NashikP51600002017· 70.9% built
- FERNDALE7.6 yr overdueAMAR JITENDRA VASANI · Deolali (CB), NashikP51600005763· 55.3% built
- GEETA HEIGHTS7.6 yr overdueGEETA DEVELOPERS · Nashik (M Corp.), NashikP51600011008· 73.6% built
- OMKAR APARTMENT7.6 yr overdueOmkar Developers · Nashik (M Corp.), NashikP51600012527· 65% built
- Param Heights7.5 yr overdueBharat Lalji Mawani · Vrindawan Nagar, NashikP51600007240· 65.5% built
- Shivam appartment7.5 yr overdueRavindra Maind · Nashik (M Corp.), NashikP51600010850· filed Mar 2018 → now Mar 2019· 69.1% built
- AADINATH PARK7.5 yr overdueSUJATA PRITESH CHHAJED · BEHED, NashikP51600015818· 81.8% built
- NANDAN SRUSHTI7.4 yr overdueHITESH RAMANBHAI PATEL · SAGAR VILLAGE, NashikP51600006992· 81.8% built
- RISHIK APPT7.4 yr overdueDARSHIT PURUSHOTTAM PATEL · Nashik, NashikP51600011144· 63.6% built
- HARI KRISHNA PHASE III7.4 yr overdueNARESH JAGUMAL KARDA · Deolaligaon, NashikP51600000375· filed Mar 2018 → now Mar 2019· 90.9% built
- GEMINI HEIGHTS II7.4 yr overdueVIKAS GEMINI · Nashik (M Corp.), NashikP51600010513· 90.9% built
- SHREE TIRUMALA HARINIWAS APARTMENT7.4 yr overdueROONGTA HOMES LLP · Satpur, NashikP51600001282· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.