All RERA projects
🏗️
Under construction

Anmol Nayantara City One Phase 1

MahaRERA P51600000539High risk

by Bafna Realtors Pvt Ltd

785/ 1 2 3/1 ,785/1 2 3/6,785/1 2 3/3/3,785/1 2 3/3/1,778/1C,778/2B P,785/1 2 3/9,784/2,785/1 2 3/1, Nashik, 422008

Official record
Dec 2018
Possession
79.6%
Built
1
Complaints
0
Units
High risk
  • Litigation pending (8). MahaRERA's litigation disclosure lists 8 pending cases against this project.
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 79.6%.
Satellite view of this address

Where it is · 785/ 1 2 3/1 ,785/1 2 3/6,785/1 2 3/3/3,785/1 2 3/3/1,778/1C,778/2B P,785/1 2 3/9,784/2,785/1 2 3/1, Nashik

Area guide

What it's like to buy in Nashik

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Bafna Realtors Pvt Ltd

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600000539
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
79.6% complete
Units sold
0 of 0

Similar projects in Nashik

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Nashik compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.