Under construction

AARYAVARTA SECTOR 4 - B TO H

MahaRERA P51600002169High risk

by LINKER SHELTER PRIVATE LIMITED

S No 980/1 plus 2/5 plus 980/1 plus 2/6 Part Plus 981/1 plus 2/3 part plus 981/1 plus 2/5 part, Nashik, 422009

Official record
Sept 2018
Possession
90.9%
Built
12
Complaints
0
Units
High risk
  • Litigation pending (11). MahaRERA's litigation disclosure lists 11 pending cases against this project.
  • 8 appeals at MahaREAT. 8 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • 12 RERA complaints. 12 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Sept 2018) has passed with construction at 90.9%.
Satellite view of this address

Where it is · S No 980/1 plus 2/5 plus 980/1 plus 2/6 Part Plus 981/1 plus 2/3 part plus 981/1 plus 2/5 part, Nashik

Promoter

Builder profile

Builder
LINKER SHELTER PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51600002169
Status
Ongoing
Stage
Certificate Signed
Possession
September 2018originally May 2018
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Nashik

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Nashik compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.