Delayed projects in Mumbai Suburban
1,523 MahaRERA-registered projects in Mumbai Suburban are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 1 of 8
- SAi JHAROKHA8.8 yr overdueSwastik Space · Borivali, Mumbai SuburbanP51800001686· filed Sept 2017 → now Dec 2017· 90.9% built
- Propose Redevelopment of Uma Smruti8.8 yr overdueJai Bhavani Constructions · Kurla, Mumbai SuburbanP51800014617· 72.7% built
- TILAK Revelopment Project of TILAK APARTMENT CHSL8.8 yr overdueKABRA AND ASSOCIATES · Andheri, Mumbai SuburbanP51800007990· 90.9% built
- Arham Aum8.8 yr overdueMahavir Enterprises · Kurla, Mumbai SuburbanP51800002719· 75.9% built· 1 complaint
- Rite Celesta8.8 yr overdueRite Developers Pvt. Ltd. · Borivali, Mumbai SuburbanP51800004974· 90.9% built
- Vighnarajendra8.8 yr overduePSC PROPERTIES PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000476· 90.9% built
- SWASTIK DISA CORPORATE PARK- 5TH TO 9TH FLOOR8.8 yr overdueSwastik Realtors · Kurla, Mumbai SuburbanP51800007796· 81.8% built
- Nirman8.8 yr overdueJPV Realtors Private Limited · Borivali, Mumbai SuburbanP51800003080· 90.9% built
- Arham Brindavan8.8 yr overdueMahavir Enterprises · Kurla, Mumbai SuburbanP51800004177· 90.9% built
- SAINATH MALAD SRA CHS8.8 yr overdueSHREE MAHALAXMI ASSOCIATES · Borivali, Mumbai SuburbanP51800004613· 90.9% built
- Modispaces Oyster8.8 yr overdueModispaces Real Estate Pvt Ltd · Borivali, Mumbai SuburbanP51800008356· 90.9% built
- PAI NIWAS8.8 yr overdueAAKAR CONSTRUCTIONS · Borivali, Mumbai SuburbanP51800012455· 90.9% built
- EDIFICE8.8 yr overdueBUILDPRO · Kurla, Mumbai SuburbanP51800006435· 55.2% built· 3 complaints
- PADMA CHS LTD8.8 yr overdueG.M.DEVELOPERS · Andheri, Mumbai SuburbanP51800002441· 90.9% built
- Gayatri Bhuvan8.8 yr overdueIndra Realtors · Borivali, Mumbai SuburbanP51800012569· 90.9% built
- BRIZO RESIDENCY8.8 yr overdueFATCAT INFRASTRCTURE PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800008276· 90.9% built· 1 complaint
- TARGET THE MALL8.8 yr overdueMAHENDRA JAMNADAS KARA · Borivali, Mumbai SuburbanP51800006542· 77.3% built· 2 complaints
- Construction of Building No 32.Shopping Center at Bimbisar nagar ,W. E. Highway,Goregaon East8.8 yr overdueMUMBAI HOUSING AND AREA DEVELOPMENT BOARD · Borivali, Mumbai SuburbanP51800000057· 54.8% built
- RAJESWARI8.8 yr overdueSHREE KRISHNA HOMES PVT LTD · Kurla, Mumbai SuburbanP51800007819· 62.3% built
- Redevelopment of Office Building no1 Sidharth Nagrar Goregaon West8.8 yr overdueMUMBAI HOUSING AND AREA DEVELOPMENT BOARD · Andheri, Mumbai SuburbanP51800000039· 71.4% built
- ROHINI RESIDENCY OF JEEVAN KUNJ CHS LTD8.8 yr overdueAARYAN REALTORS · Kurla, Mumbai SuburbanP51800012290· 90.9% built
- Construcion of 28 LIG tenement on Plot OB 8,Siddharth nagar ,Goregaon west,Mumbai8.8 yr overdueMUMBAI HOUSING AND AREA DEVELOPMENT BOARD · Borivali, Mumbai SuburbanP51800000031· 90.9% built· 2 complaints
- DHARTI SRA8.8 yr overdueMILAN NEMJI GALA · Borivali, Mumbai SuburbanP51800008701· 90.9% built
- SAMYAKTH BLISS BUILDING 28.8 yr overdueSamyakth Realties · Andheri, Mumbai SuburbanP51800013227· 90.9% built
- Gokul Gagan Apartments8.8 yr overdueAraddhana Enterprises · Borivali, Mumbai SuburbanP51800011276· 90.9% built
- SHANTI SADAN8.8 yr overdueMAN GLOBAL LTD. · Andheri, Mumbai SuburbanP51800008793· 90.9% built· 7 complaints
- SAI GABHASTI8.8 yr overdueAndheri, Mumbai SuburbanP51800005461· 80% built
- REDEVELOPMENT OF KRIPADHAM CHS LTD8.8 yr overdueKRIPA REALTORS · Borivali, Mumbai SuburbanP51800013163· 90.9% built
- Rite Prime8.8 yr overdueRite Developers Pvt. Ltd. · Andheri, Mumbai SuburbanP51800010472· 90.9% built
- ORION8.8 yr overdueNivaan Infratech Private Limited · Kurla, Mumbai SuburbanP51800000279· 86.4% built
- GORAI MITASU8.8 yr overdueSumit Woods Pvt. Ltd. · Borivali, Mumbai SuburbanP51800005404· 90.9% built
- SPENTA8.8 yr overdueSVK PROJECTS LLP · Andheri, Mumbai SuburbanP51800000892· 90.9% built
- THE VRINDAVAN NAGAR CHS LTD8.8 yr overdueAMI HOUSING LIMITED · Kurla, Mumbai SuburbanP51800009398· 90.9% built
- RUDRANSH8.8 yr overdueSPA JAIN REAL ESTATE PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800004422· 90.9% built
- REDEVELOPMENT OF THE STATE BANK OF INDIA SIDDHESHWAR CO OP HOUSING SOC LTD8.8 yr overdueORRA REALTORS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800010846· 80.9% built
- Cosmopolis Phase 18.8 yr overdueCosmos Homes India Pvt. Ltd. · Andheri, Mumbai SuburbanP51800012114· 72.7% built· 5 complaints
- Parsh Galaxy8.8 yr overduePARSH HOUSING PVT LTD · Borivali, Mumbai SuburbanP51800008099· 90.9% built
- VIOLETTE VALLEY8.8 yr overdueAQUA MARINE ENTERPRISES · Mumbai, Mumbai SuburbanP51800011664· 90.9% built
- Mahavir Aria8.8 yr overdueMilestone Developers · Kurla, Mumbai SuburbanP51800000409· 72.7% built
- KRISHNA NIWAS8.8 yr overdueSHREE KRISHNA HOMES PVT LTD · Kurla, Mumbai SuburbanP51800008073· 90.9% built
- Kenorita Jewels8.8 yr overdueK R Shoppers Pvt. Ltd. · Borivali, Mumbai SuburbanP51800013176· 99.5% built
- SAI ASHISH II8.8 yr overdueKUKREJA CONSTRUCTION CO · Kurla, Mumbai SuburbanP51800009725· 72.7% built
- Rajal - Om Jaishriram CHS Ltd8.8 yr overdueNisar Properties Private Limited · Kurla, Mumbai SuburbanP51800002124· 90.9% built· 12 complaints
- GUNDECHA TRILLIUM8.8 yr overdueSEA PRINCESS REALTY · Borivali, Mumbai SuburbanP51800001115· 97% built· 16 complaints
- MODI HOUSE8.8 yr overdueMODI ENTERPRISE · Borivali, Mumbai SuburbanP51800000872· 90.9% built
- Priya Girish Vihar CHS Ltd8.8 yr overdueAmeya Developers · Kurla, Mumbai SuburbanP51800006961· 90.9% built
- SHREE MANGAL8.8 yr overdueMANGAL BUILDHOME PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800004380· 90.9% built
- CONST OF 586 EWS 234 MIG TENAMENTS ON LAND BEARING CTS NO 1 C 1 1 BORIVALI WEST MUMBAI 678.8 yr overdueMAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY · Borivali, Mumbai SuburbanP51800008549· 90.9% built
- Sky Residency Loksadan CHS Phase 1 Up to G Plus 7pt.8.8 yr overdueSky Property Developers Private Limited · Borivali, Mumbai SuburbanP51800003387· 90.3% built· 1 complaint
- OM SHREE SAIDHAM8.8 yr overdueS K ENTERPRISE · Kurla, Mumbai SuburbanP51800003439· 81.8% built
- AAKASHA CHSL8.8 yr overdueTrivenidevelopers · Borivali, Mumbai SuburbanP51800007596· 78.6% built
- SOLITAIRE8.8 yr overdueRAJENDRA PUNDLIKRAO GODSHALWAR · Andheri, Mumbai SuburbanP51800013228· 90.9% built
- Lotus Prestige8.8 yr overdueEssen Builders and Developers · Borivali, Mumbai SuburbanP51800011399· 90.9% built
- GHANSHAM HEIGHT8.8 yr overdueGHANSHAM PROPERTIES · Borivali, Mumbai SuburbanP51900014250· 90.9% built
- Kush Prestige8.8 yr overdueKush Buildcon LLP · Andheri, Mumbai SuburbanP51800002724· 90.9% built
- GEETANJALI8.8 yr overdueKUKREJA CONSTRUCTION CO · Kurla, Mumbai SuburbanP51800000280· 72.7% built
- Lodha Fiorenza8.7 yr overdueLODHA DEVELOPERS LIMITED · Borivali, Mumbai SuburbanP51800000195· 90.9% built· 5 complaints
- TORNA APARTMENT8.7 yr overdueRAJMUDRA CONSTRUCTION PVT LTD · Borivali, Mumbai SuburbanP51800009548· 90% built
- OM PALACE8.7 yr overdueMADHUSUDAN SITARAM JUNNARKAR · Borivali, Mumbai SuburbanP51800007960· 90.9% built
- ONYX APARTMENT - REDEVELOPMENT OF KUNFAYAKUN CHSL BUILDING8.7 yr overdueReFAB CONSTRUCTION (INDIA) PVT. LTD. · Borivali, Mumbai SuburbanP51800007695· 68.7% built
- MILAP CO-OPERATIVE HOUSING SOCIETY8.6 yr overdueGOLDEN EYECON · Andheri, Mumbai SuburbanP51800001191· 90.9% built
- Jeevan Kanchan Co-Operative Housing Society Ltd.8.5 yr overdueShri Krishna Chaitanya Enterprises · Andheri, Mumbai SuburbanP51800000014· 90.9% built
- Rachanaa Solitaire8.5 yr overdueRACHANAA REALTORS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800002008· 90.9% built
- Hillcrest A Wing8.5 yr overdueHillcrest Joint Venture · Andheri, Mumbai SuburbanP51800002556· 97.6% built· 4 complaints
- GULRAJ HEIGHTS8.5 yr overdueM/S NEETA DEVELOPER · Kurla, Mumbai SuburbanP51800009977· 90% built
- Dhoot Emrald Residency-Jaygun Sagar CHSL8.5 yr overdueDHOOT DEVELOPERS PVT. LTD. · Kurla, Mumbai SuburbanP51800003713· 76.4% built
- ZEN APARTMENTS8.5 yr overdueBHOLENATH DEVELOPERS LTD. · Kurla, Mumbai SuburbanP51800002227· 90.9% built
- KENORITA GARMENT HUB8.5 yr overdueKeshvi Developers Pvt Ltd · Andheri, Mumbai SuburbanP51800011101· 82.3% built
- CVII8.5 yr overduePARDIS CONSTRUCTION LLP · Kurla, Mumbai SuburbanP51800011608· 90.9% built
- Kesarban8.5 yr overdueAmbrosial Developers Private Limited · Andheri, Mumbai SuburbanP51800001181· 90.9% built
- Suvidha CHS Ltd8.5 yr overdueAmi & Monika Developers · Kurla, Mumbai SuburbanP51800004792· 80.9% built
- Rajal - Frances CHS Ltd8.5 yr overdueNisar Properties Private Limited · Borivali, Mumbai SuburbanP51800001672· 90.9% built
- SHELTON B8.5 yr overduePatel Construction co · Andheri, Mumbai SuburbanP51800002799· 72.7% built
- SRISHTI OASIS PH 1 WING A PALMS8.5 yr overdueSHIV KRUPA ENTERPRISE · Kurla, Mumbai SuburbanP51800003982· 90.9% built
- MEGHDOOT RESIDENCY8.5 yr overdueMILAN INTERBUILT PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800003357· 90.9% built
- VINAYAK PARADISE8.5 yr overdueAVANI DEVELOPERS · Kurla, Mumbai SuburbanP51800005258· 90.9% built
- SAKET RESIDENCY CO OP HSG SOC LTD8.5 yr overdueREGENT BUILDERS · Andheri, Mumbai SuburbanP51800007061· 85.5% built
- Skyline wealthspace Wing C2 3 to 8 floors8.5 yr overdueSymphony · Kurla, Mumbai SuburbanP51800004870· 90.9% built
- ESPERENZA8.5 yr overdueSPLENDOUR REALTORS INDIA PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800008847· 99.1% built
- Malwani Sea View CHS LTD8.5 yr overdueMalwani Sea View CHS LTD · Borivali, Mumbai SuburbanP51800012674· 90.9% built
- Pampa Co-Operative Housing Society8.5 yr overdueARHAM REALTORS LLP · Goregaon West, Mumbai SuburbanP51800004869· 90.9% built
- Malwani Asha Jeevan CHS LTD8.5 yr overdueMalwani Asha Jeevan CHS LTD · Borivali, Mumbai SuburbanP51800012990· 90.9% built
- Vile Parle Kalpavriksha cooperative Housing Society Limited8.5 yr overdueRelcon Infraprojects Ltd · Andheri, Mumbai SuburbanP51800000188· 90.9% built
- SHREE RAM8.5 yr overdueRACHANAA · Kurla, Mumbai SuburbanP51800001464· 90.9% built
- LOVEDALE RESIDENCES8.5 yr overdueYASHODHAN UNIQUE CONSTRUCTION COMPANY · Borivali, Mumbai SuburbanP51800007324· 99.6% built
- Redevelopment of Transit Building No 32 and 33 Sidharth Nagar Goregaon West8.5 yr overdueMUMBAI HOUSING AND AREA DEVELOPMENT BOARD · Andheri, Mumbai SuburbanP51800000030· 56.7% built
- Rosary Villa Co Operative Housing Society Limited8.5 yr overdueJay Vee Construction · Borivali, Mumbai SuburbanP51800009021· 72.7% built· 4 complaints
- JYOTI8.5 yr overdueV R ASSOCIATES · Andheri, Mumbai SuburbanP51800004260· 90.9% built
- PLLATINUM AURA8.5 yr overdueG.S. DEVELOPERS · Andheri, Mumbai SuburbanP51800003297· 90.9% built· 1 complaint
- Construction of 94 EWS Ts and 182 LIG Ts on CTS No 43 Unnatnagar Goragaon west8.5 yr overdueMUMBAI HOUSING AND AREA DEVELOPMENT BOARD · Andheri, Mumbai SuburbanP51800000042· 72.7% built
- Nayana Niwas8.5 yr overdueH.D.Associates · Borivali, Mumbai SuburbanP51800004622· 60% built
- THAIS RESIDENCY8.5 yr overdueMERCHANT CONSTRUCTIONS PVT. LTD. · Andheri, Mumbai SuburbanP51800011454· filed Dec 2017 → now Mar 2018· 70.5% built· 6 complaints
- New Mahavir Darshan Chsl8.5 yr overdueLMP GROUP · Borivali, Mumbai SuburbanP51800012191· 54.1% built
- Malwani West View CHS LTD8.5 yr overdueMalwani West View CHS LTD · Borivali, Mumbai SuburbanP51800012895· 90.9% built
- Gyan Kutir8.5 yr overdueSungreens Corp · Borivali, Mumbai SuburbanP51800006548· 90.9% built
- Construction of 232 LIG TS on S.No. 263 p C.T.S No. 3525p Nr Bus depo Malwani Malad west Mumbai 958.5 yr overdueMUMBAI HOUSING AND AREA DEVELOPMENT BOARD · Borivali, Mumbai SuburbanP51800000033· 90.9% built· 1 complaint
- SHRADDHA ORCHID AVENUE8.5 yr overdueSHRADDHA LANDMARK PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800012384· filed Dec 2017 → now Apr 2018· 89.5% built· 1 complaint
- Shaswat Residency8.5 yr overdueShaswat Realty · Kurla, Mumbai SuburbanP51800008668· 44.5% built
- Harshail Dhanuka Residency8.5 yr overdueHARSHMAAN CONSTRUCTION · Andheri, Mumbai SuburbanP51800000368· 81.8% built
- JAI GOPI KRISHNA CHSL8.5 yr overdueNav Durga Construction Company · Kurla, Mumbai SuburbanP51800006482· filed Dec 2017 → now Apr 2018· 90.9% built
- SUMMERSET8.5 yr overdueNEO HOUSING AND INFRASTRUCTURE DEVELOPMENT LIMITED · Borivali, Mumbai SuburbanP51800008467· filed Dec 2017 → now Apr 2018· 88.6% built
- REDEVELOPMENT OF SBI EMPLOYEES KANCHAN MRIG CHS LTD.8.5 yr overdueR R CONSTRUCTIONS · Andheri, Mumbai SuburbanP51800003186· 90.9% built
- DLH METROVIEW8.5 yr overdueDEV LAND & HOUSING PRIVATE LIMITED · ANDHERI WEST, Mumbai SuburbanP51800005170· 81.8% built· 1 complaint
- GLORIS RESIDENCY8.4 yr overdueSahakar Developers · Borivali, Mumbai SuburbanP51800003895· 90.9% built
- GUNDECHA ASTA PHASE I8.4 yr overdueAnaya Infrastructure Pvt. Ltd. · Andheri, Mumbai SuburbanP51800001504· 88.6% built· 1 complaint
- Mahavir Solitaire8.4 yr overdueInfinity Construction Co. · Kurla, Mumbai SuburbanP51800000404· 78.6% built
- Plot No 888.4 yr overdueJitesh Bhawarlal Jain · Borivali, Mumbai SuburbanP51800006523· 87.3% built
- PEARL HAZELINE8.4 yr overdueCHANDIWALA ENTERPRISES · Andheri, Mumbai SuburbanP51800003301· 90.9% built
- 64 LIG, 80 MIG, 16HIG and 20 Shops at Sr. No. 491, Res. No. 23 Part, Vengurla, Dist. Sindhudurg8.4 yr overdueMAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY · Andheri, Mumbai SuburbanP51800002323· 69.3% built
- LAXMI VILLA8.4 yr overdueLAXMIDEVI DEVELOPERS · Borivali, Mumbai SuburbanP51800002675· 90.9% built
- BORIVALI SAHAKAR NIKETAN8.4 yr overdueAMAR ENTERPRISES · Borivali, Mumbai SuburbanP51800011527· 69.5% built· 1 complaint
- AZAD NAGAR SHUBHAM CHSL8.3 yr overduePRATHAMESH KRUPA BUILDCON PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800006313· filed Dec 2017 → now Jun 2018· 72.7% built
- Raj Nirman8.3 yr overdueFERRO BUILD · Borivali, Mumbai SuburbanP51800003531· 55.5% built
- GEM PLAZA8.3 yr overdueGEM PATH DEVELOPERS · Andheri, Mumbai SuburbanP51800011279· 90.9% built
- SAI VAIBHAV8.3 yr overdueANIL GANGARAM SAWANT · Borivali, Mumbai SuburbanP51800011223· filed Mar 2018 → now Jun 2018· 90.5% built
- SAFALYA8.3 yr overdueVITAE CONSTRUCTIONS LLP · Andheri, Mumbai SuburbanP51800004205· 79.5% built
- 16th Avenue8.3 yr overdueMNK Builders LLP · Andheri, Mumbai SuburbanP51800005930· 88.2% built
- Bhushan Enclave CHSL8.3 yr overdueBhushan Enterprises · Borivali, Mumbai SuburbanP51800012821· 90.9% built
- Simba Tower8.3 yr overdueSimba Enterprises LLP · Borivali, Mumbai SuburbanP51800008506· filed Dec 2017 → now Jun 2018· 90.9% built
- Siddharth Nagar Sukhvilla CHS Ltd8.3 yr overdueDILIP HIRALAL DOSHI · Borivali, Mumbai SuburbanP51800009426· 99.7% built· 1 complaint
- ESQUIRE SKYTOWER8.3 yr overdueCOSMOS ASHWAMEDH JOINT VENTURE · Kurla, Mumbai SuburbanP51800005840· 67.3% built
- VIJAYLAXMI BLISS8.3 yr overdueVIJAYLAXMI INFRACON LLP · Andheri, Mumbai SuburbanP51800000896· 76.4% built
- Sharda Sahaniwas8.3 yr overdueSumit Chetna Ventures · Borivali, Mumbai SuburbanP51800002134· filed Mar 2018 → now Jun 2018· 98.6% built· 1 complaint
- ADVENT PALAZZO8.3 yr overdueADVENT DEVELOPERS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800002649· 86.4% built· 1 complaint
- DEVI CLASSIC8.3 yr overdueD M REALITY · Kurla, Mumbai SuburbanP51800002600· 90.9% built
- SWATI C.H.S. LTD8.3 yr overdueDILIP HIRALAL DOSHI · Borivali, Mumbai SuburbanP51800007302· 90.5% built
- APURVA RESIDENCIES8.3 yr overdueSTARWING DEVELOPERS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000167· 90.8% built
- SHRI GANESH APARTMENTS8.3 yr overdueMATUSHREE REAL ESTATE DEVELOPERS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800004536· filed Dec 2017 → now Jun 2018· 72.7% built· 1 complaint
- OM SHUBH LABH8.3 yr overdueBALI REALTY LLP · Borivali, Mumbai SuburbanP51800006707· 90.9% built
- MERIDEAN ASSOCIATES8.3 yr overdueMERIDEAN ASSOCIATES · Kurla, Mumbai SuburbanP51800003813· filed Dec 2017 → now Jun 2018· 81.8% built
- DARPAN HEIGHTS8.3 yr overdueDUDHAL INFRA · Borivali, Mumbai SuburbanP51800009866· 88.2% built
- Rohan Development8.2 yr overdueM/s Rohan Development · Borivali, Mumbai SuburbanP51800004819· 90.9% built· 15 complaints
- DIWAPRABHU RESIDENCY8.2 yr overdueDiwaprabhu Homes · Borivali, Mumbai SuburbanP51800004311· 90.9% built
- STAR SKY DHANLAXMI DEVELOPERS8.2 yr overdueSTAR SKY DHANLAXMI DEVELOPERS · Kurla, Mumbai SuburbanP51800008867· 90.9% built
- VISHWAVILLA8.2 yr overdueGLASSWOOD AND LUCKY DEVELOPERS · Borivali, Mumbai SuburbanP51800012317· 72.7% built
- Gurbani B8.2 yr overdueHeena Construction Co · Kurla, Mumbai SuburbanP51800010088· 86.4% built
- MADHUKUNJ8.2 yr overdueDHARA CONSTRUCTION · Borivali, Mumbai SuburbanP51800007837· filed Mar 2018 → now Jul 2018· 81.8% built
- REDEVELOPMENT OF RAJENDRA APARTMENTS CHSL8.2 yr overduePRANAV CONSTRUCTIONS LIMITED · Borivali, Mumbai SuburbanP51800002378· 90.9% built
- SIGNATURE8.2 yr overdueLAKHANI BUILDERS PVT LTD · Mumbai, Mumbai SuburbanP51800001227· 90.5% built· 1 complaint
- SHREE SATI ASHISH CO OP HOUSING SOCIETY8.2 yr overdueSUN-VUB · Kurla, Mumbai SuburbanP51800007372· 80% built
- BEAUTY LANDMARK8.2 yr overdueBEAUTY GANRAJ CONSTRUCTION LLP · Kurla, Mumbai SuburbanP51800008233· 90.9% built
- Bajaj Enchante - Panchsheel CHSL8.2 yr overdueBAJAJ INTERNATIONAL REALTY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000817· filed Dec 2017 → now Jul 2018· 90.9% built
- UNITY HEIGHTS8.2 yr overdueUNITED DEVELOPERS · Borivali, Mumbai SuburbanP51800008199· 90.9% built
- AMAR GEEJAY CO OPERATIVE HOUSING SOCIETY LIMITED8.2 yr overdueK T SONS · Borivali, Mumbai SuburbanP51800002603· 90.5% built· 2 complaints
- Polys Cooperative Housing society8.2 yr overduePARSH HOUSING PVT LTD · Borivali, Mumbai SuburbanP51800009952· 59.1% built
- PRATIMA CO-OPERATIVE HOUSING SOCIETY8.2 yr overdueSUBHASH VELJI CHAWDA · Andheri, Mumbai SuburbanP51800010091· 21.5% built
- Jaylaxmi CHSL8.1 yr overdueJaywant Ramchandra Keni · Borivali, Mumbai SuburbanP51800005945· 90.9% built
- Matoshree Park8.1 yr overdueSHREE TRUPATI BALAJI REALTORS · JUVELI VILLAGE, Mumbai SuburbanP51800007951· 55.5% built
- One8.1 yr overdueE D Developers Private Limited · Andheri, Mumbai SuburbanP51800011338· 90.9% built
- Paramount8.0 yr overduePrakash Housing Pvt Ltd · Kurla, Mumbai SuburbanP51800003917· 90.9% built
- HANS ELEGANCE8.0 yr overdueSHREE HANS REALTORS LLP · Andheri, Mumbai SuburbanP51800003370· 56.4% built
- Peninsula Technopark Building D8.0 yr overdueSwan Energy Limited · Kurla, Mumbai SuburbanP51800001195· 81.8% built
- GOLDEN STAR RESIDENCY BUILDING NO 28.0 yr overdueARUNDHATI AJAY KADAM · CHIPLUN, Mumbai SuburbanP51800005343· 90.9% built
- Anand Bhavan - Pristino8.0 yr overdueShri Sati Builders and Developers Private Limited · Kurla, Mumbai SuburbanP51800008855· filed Dec 2017 → now Sept 2018· 81.8% built
- NIDHAAN CINEPLAZA8.0 yr overdueM/S. NIDHAAN BUILDCON PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800014315· 63.2% built
- UPKAR CHS LTD8.0 yr overdueTEJAS DINESH SHAH · Borivali, Mumbai SuburbanP51800010621· 80.5% built
- Odhav Baug8.0 yr overdueS. K. CONSTRUCTION · Kurla, Mumbai SuburbanP51800011780· 68.2% built
- NAVJEEVAN HEIGHTS8.0 yr overdueKonark Shakti Group of Companies · malad east, Mumbai SuburbanP51800010116· 90.9% built
- Redevelopment of Prateeksha CHS Ltd8.0 yr overdueASHIANA ENTERPRISES · Borivali, Mumbai SuburbanP51800016261· 90.9% built
- TRIVENI8.0 yr overdueSHREENATH INFRAPROJECTS · Andheri, Mumbai SuburbanP51800010070· filed Mar 2018 → now Sept 2018· 82.8% built
- Medinee CHS Ltd8.0 yr overdueShamik Enterprises Pvt Ltd. · Andheri, Mumbai SuburbanP51800001664· filed Dec 2017 → now Sept 2018· 90.9% built
- AHIMSA HEIGHTS8.0 yr overdueAHIMSA BUILDER · Borivali, Mumbai SuburbanP51800007486· 72.7% built· 3 complaints
- DELHOUSE CO.OP. HSG. SOC.LTD.8.0 yr overdueAUM SHIV ENTERPRISES · Andheri, Mumbai SuburbanP51800002780· 90.9% built
- Mulund Mahavir Darshan8.0 yr overdueChheda Lifestyles · Kurla, Mumbai SuburbanP51800002234· 72.7% built
- SUDHANSHU CHS LTD8.0 yr overdueHARIOM DEVELOPERS · Andheri, Mumbai SuburbanP51800004339· 90.9% built
- SHREE GANESH RACHANA8.0 yr overdueRAJAN CHANDRAKANT TIPNIS HUF · Kurla, Mumbai SuburbanP51800003279· 67.5% built
- SARLA AVENUE8.0 yr overdueSANDEEP MAHENDRA KANAKIA · Borivali, Mumbai SuburbanP51800002489· 90.9% built
- Chaitanya Residency8.0 yr overdueEthics Infra Development Pvt Ltd · Borivali, Mumbai SuburbanP51800000886· filed Apr 2018 → now Oct 2018· 81.8% built
- 92 BELLEVUE8.0 yr overdueNRS Developers · Borivali, Mumbai SuburbanP51800006106· 90.9% built
- A-14, A Wing Petunia Apts, Bindra Complex8.0 yr overdueAccord Land Developers Pvt Ltd · Andheri, Mumbai SuburbanP51800003133· 90.9% built
- Bhaveshwar Arcade Annexe7.9 yr overdueBhaveshwar Properties Pvt Ltd · Kurla, Mumbai SuburbanP51800000967· 90.9% built
- SIDDHACHAL MALAD MAMLETDARWADI7.9 yr overdueBUCON ENGINEERS & INFRASTRUCTURE PVT. LTD. · Borivali, Mumbai SuburbanP51800008815· filed Dec 2017 → now Dec 2018· 90.9% built
- Shree Dattakrupa Height Buidling No 1257.9 yr overdueEkdanta Constructions Pvt Ltd · Kurla, Mumbai SuburbanP51800012504· 89.1% built
- Construction of 86 Tenements out of 430 MIG tenements of old Magathane village Borivali7.8 yr overdueMAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY · Borivali, Mumbai SuburbanP51800000063· 90.9% built
- USHA KAAL7.8 yr overdueMILIND KESARINATH RAUL · Kurla, Mumbai SuburbanP51800008807· 67.5% built· 4 complaints
- BHushan Plaza CHSL7.8 yr overdueBhushan Enterprises · Borivali, Mumbai SuburbanP51800012726· 90.9% built
- OM SHRI SHANTIKUNJ7.8 yr overdueADITYA ENTERPRISES · Kurla, Mumbai SuburbanP51800009006· 73.9% built· 4 complaints
- GANESHYOG CHS7.8 yr overdueAARUNI HARISHCHANDRA PATIL · Borivali, Mumbai SuburbanP51800006281· 55.5% built
- Amar CHSL7.8 yr overdueShiva Shakti Enclaves Private Limited · Andheri, Mumbai SuburbanP51800003597· 53.9% built· 2 complaints
- Grace Luxuria7.8 yr overdueNew India Construction Co · Borivali, Mumbai SuburbanP51800004501· 90.9% built· 3 complaints
- Modispaces Doyle7.8 yr overdueModispaces Real Estate Pvt Ltd · Borivali, Mumbai SuburbanP51800006618· 90.9% built
- AMI CHSL7.8 yr overdueMEHTA GROUP · Borivali, Mumbai SuburbanP51800008106· 72.7% built
- EVERSHINE MADHUVAN7.8 yr overdueEVERSHINE BUILDERS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000687· 90.9% built
- AARADHYA ONE7.8 yr overdueAM DEVELOPERS · Kurla, Mumbai SuburbanP51800000333· 89.4% built
- SHIVDARSHAN SRA CHS LTD7.8 yr overdueSHREE SWAMI SAMARTH BUILDERS · Kurla, Mumbai SuburbanP51800011946· 95.3% built
- MAHALAXMI PRASAD BUILDING7.8 yr overdueSUDHEER DADARKAR · Borivali, Mumbai SuburbanP51800002525· 95.5% built
- PEARL BELLEZA7.8 yr overdueCHEMBUR HOTELS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800001897· 77.7% built
- Subham Bileshwar7.8 yr overdueSubham Developers · Ghatkopar (East), Mumbai SuburbanP51800013930· 90.9% built
- Gurnani Palms Wing A7.8 yr overdueInterintel Constructions · Andheri, Mumbai SuburbanP51800005611· 90.8% built
- VIRANGULA CHS LTD7.8 yr overdueRISHABRAJ HOUSING · Borivali, Mumbai SuburbanP51800004450· 85.9% built
- PATEL ASSOCIATES7.8 yr overduePURSHOTTAM KALUBHAI PATEL · Borivali, Mumbai SuburbanP51800013348· 89.2% built
- TIMMY RESIDENCY7.8 yr overdueHARVINDERPAL TIRATHPAL MEHTA · Andheri, Mumbai SuburbanP51800012112· filed Dec 2017 → now Dec 2018· 72.7% built
- KABRA PARADISE7.8 yr overdueKABRA ESTATE AND INVESTMENT CONSULTANTS · Andheri, Mumbai SuburbanP51800000684· 90.9% built
- SHREE SAMARTH GALAXY SRA CHS LTD7.8 yr overdueShree S S Developers Private Limited · Kurla, Mumbai SuburbanP51800009435· 90.9% built
- SIDDH DARSHAN7.8 yr overdueDEEP ASSOCIATES · Kurla, Mumbai SuburbanP51800006988· 56.4% built
- RAJ EKJYOT SUKRUTI7.8 yr overdueSADGUNA REALTY · Kurla, Mumbai SuburbanP51800006006· 90.2% built
- SABARI ASHVILLE7.8 yr overdueSABARI JANI ASSOCIATES · Kurla, Mumbai SuburbanP51800003066· filed Dec 2017 → now Dec 2018· 99.9% built· 1 complaint
- MYRIAX TOWER7.8 yr overdueMYRIAX INFRATECH PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800007754· 72.7% built
- Whitespring7.8 yr overdueCCI PROJECTS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800002287· 99.2% built· 10 complaints
- DHARMANATH KRUPA7.8 yr overdueBALI LANDMARKS LLP · Borivali, Mumbai SuburbanP51800007747· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.